Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2006 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 03/31/2006 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. DISCONNECTS FOR EQUIP. TO BE IN COMPLIANCE WITH 110-26 NEC WORKING CLEARANCE 30" HORIZONTAL, 36" IN FRONT 2. BUBBLE COVERS REQUIRED FOR GFI OUTLETS EXPOSED TO DAMP CONDITIONS. 3. INSULATING BUSHINGS REQUIRED ON CONDUCTORS #4 AND LARGER. 4. BOND NEUTRAL IN X-FORMER |
|
| 03/24/2006 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 03/23/2006 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* NOTE 1. PARALLEL FEEDERS TO CONTAIN PARALLEL NEUTRALS AS PER 310.4 2. BOND NEUTRAL IN PANEL AT SERVICE. |
|
| 03/21/2006 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* NOTES 1. BOND BUSHINGS REQUIRED ON ALL NIPPLES AHEAD OF OVER CURRENT PROTECTION AT SERVICE 2. EQUIP GROUNDS TO BE SIZED PER 250 NEC AT CT CAN BOND BUSHINGS 3. NEED PLAN 4. RUN OR INSTALL EQUIP. GROUNDS IN EACH SET OF PARALLEL FEEDERS PER NEC 5. NEUTRALS TO BE RUN TO SERVICE DISCONNECTING MEANS PER 250.24 - 250.28 6. CONTR. TO VERIFY GUTTER SIZE FOR CONDUCTORS INSTALLED PER 366.6 7. ALL PLAN REVISIONS TO BE APPROVED THRU COT PLAN REVIEW. |