Permit: T05CM04308
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
7415 E TANQUE VERDE RD
Address NEW:
7415 E TANQUE VERDE RD
Apply Date:
08/17/2005
Applicant:
N/A
Description:
NEW OFFICE
Architects:
- EGLIN, EVAN SAR
Contractors:
- VENTURE WEST INC
Permit Reviews
Permit Number - T05CM04308
Permit Status: C of o
Permit Description: NEW OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/18/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 01/20/2006 | COMPLETED |
| 08/17/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 08/26/2005 | COMPLETED |
| 08/26/2005 | 3RD PARTY REVIEW-COMMERCIAL | 10/17/2005 | COMPLETED |
| 10/17/2005 | POST 3RD PARTY REVIEW | 10/18/2005 | COMPLETED |
| 12/06/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 12/14/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04308
Permit Status: C of o
Permit Description: NEW OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/17/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM04308
Permit Description: NEW OFFICE
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :*SOIL WATER TEST IS OK HCS CONNECTION IS OK OK TO BACKFILL TRENCH |
| 11/15/2005 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection :* |
| 12/13/2005 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK UNDERGROUND RIGID FOR DENTAL CHAIRS (4 CHAIRS) (5 INWALLS) |
| 12/13/2005 | PLUMBING - MEDICAL GAS/TEST | RMYERS | Approved | IVRS - Inspection :* 1. LEVEL THREE - COMP. AIR - NO SLEEVE REQUIRED VACUUM SCH TO PVC PIPING WRAPPED THROUGH CONCRETE CONTRACTOR TO REALIGN CHANGES FROM THE PLAN OK TO COVER, SUBJECT TO SPECIAL INSPECTOR DON'T FORGET TO SCHEDULE AN INSPECTION WHEN INTERIOR PIPING BEGINS. |
| 12/15/2005 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :* |
| 12/15/2005 | BUILDING PRE-SLAB | JCAGLE | Approved | IVRS - Inspection :* |
| 12/29/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :* CANOPY COLUMN FOOTINGS |
| 02/14/2006 | ROOF NAILING | JCAGLE | Approved | IVRS - Inspection :* |
| 02/17/2006 | EXT METAL CLIPS/EXT SHEATHING | JCAGLE | Approved | IVRS - Inspection :* WILL VERIFY HOLDDOWN & ANCHOR BOLTS SPACING WITH FRAMING (01035) |
| 03/03/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUSPENDED ROUGH DUCT, EXHAUST FANS CONDENSATE DRAINS OK OK TO SHEETROCK |
| 03/03/2006 | FRAMING | JCAGLE | Approved | IVRS - Inspection :* OK TO SHEETROCK |
| 03/07/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* WATER TEST WASTE & VENT THRU ROOF OK WATER PIPING OK CLOSET FLANGES OK |
| 03/15/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 03/15/2006 | REINFORCED MASONRY PRE-GROUT | JCAGLE | Approved | IVRS - Inspection :* |
| 03/17/2006 | STUCCO MESH | JCAGLE | Approved | IVRS - Inspection :* |
| 03/20/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 04/19/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
| 04/19/2006 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 04/20/2006 | TEP CLEARANCE - AM | BFLORES | Approved | CEC PER R.HOLLANDER |
| 04/27/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
| 05/10/2006 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* TILES ALREADY IN PLACE IN MOST AREAS |
| 05/31/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/12/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |
| 06/12/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 06/12/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 06/14/2006 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 06/14/2006 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 06/14/2006 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection :* |
| 06/14/2006 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 06/14/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 06/15/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* OK FINAL |
| 06/15/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/15/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 07/18/2006 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* FINALED ON 6/15/06 |
| 07/18/2006 | U VALUE FOR WINDOW | JBURGE | Approved | PER FINAL |
| 08/03/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 08/09/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 08/09/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 08/14/2006 | PERMIT FINALED | DROBEY | Approved |