| 08/03/2006 | ENGINEERING - FINAL | Approved | ||
| 08/02/2006 | ENGINEERING - FINAL | Cancelled | IVRS - AP canceled | |
| 07/19/2006 | ENGINEERING - FINAL | Partial Approval | OK FOR 30 DAY EXTENSION OF THE TEMPORARY C OF O . 1. COMPLETE SITE WORK IDENTIFIED ON THE 5/10/06 INTERMEDIATE GRADING INSPECTION OF "INFORMAL" PHASE I, THAT INCLUDED LOTS 15-23 AND 38-49. 2. CONSTRUCT VERTICAL CURB AT HANDICAP PARKING TO DETAIL I SPECIFICATIONS. 3. PROVIDE 6" STORMWATER HARVEST AREAS IN MEDIAN ISLANDS AS SHOWN ON THE PLAN. KEYNOTE 27. 4. PROVIDE BICYCLE PARKING AT (9) LOCATIONS AS SHOWN ON THE PLAN. 5. PROVIDE A CERTIFICATION LETTER FROM THE ENGINEER THAT CERTIFYS THE ENTIRE PROJECT. |
|
| 06/14/2006 | ENGINEERING - FINAL | Approved |