Permit: T05CM02538
Permit Details
Apply Date:
06/03/2005
Applicant:
N/A
Description:
NEW: PANDA EXPRESS (RESTAURANT)
Contractors:
- YARBOROUGH DEVELOPMENT INC
Permit Reviews
Permit Number - T05CM02538
Permit Status: C of o
Permit Description: NEW: PANDA EXPRESS (RESTAURANT)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/03/2005 | PLANS OK TO SUBMIT - COMM | 06/03/2005 | COMPLETED |
06/03/2005 | PLANS OK TO SUBMIT - SITE | 06/03/2005 | COMPLETED |
06/03/2005 | 3RD PARTY REVIEW-COMMERCIAL | 07/22/2005 | COMPLETED |
07/22/2005 | POST 3RD PARTY REVIEW | 08/04/2005 | COMPLETED |
07/28/2005 | SITE | 08/04/2005 | COMPLETED |
09/21/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 09/22/2005 | COMPLETED |
11/15/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 11/17/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM02538
Permit Status: C of o
Permit Description: NEW: PANDA EXPRESS (RESTAURANT)
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/03/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM02538
Permit Description: NEW: PANDA EXPRESS (RESTAURANT)
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/25/2005 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
08/26/2005 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
09/02/2005 | ELECTRIC - TEMPORARY SERVICE | RSUBA | Approved | IVRS - Inspection :* 1) OK TO CLEAR |
09/08/2005 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1) PIPE WRAPS AND TRAP PRIMERS OK |
09/08/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
09/28/2005 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
10/06/2005 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :*2" FROM METER THRU BACKFLOW INTO BUILDING OK. |
10/10/2005 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
10/12/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* CHECKED CONDENSATE DRAIN LINES, SUPPLY & EXHAUST IN RESTROOMS. INSULATE DUCT INSIDE BLDG. WITH MIN R-5 OK FOR SHEET ROCK. |
10/12/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* YOU MAY NOT HAVE KRAFT ?? OF INSULATION EXPOSED. IT MUST BE TIGHT TO SHEATHING OR ROCK. |
10/12/2005 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* 2 1/2 FROM METER ,1 1/2 THRU ROOF ( CAPPED AT THIS TIME) CONTINUES THRU ANSUL VALVE & COOKING BATTERY OK . 15 PSI TEST. NEED TO SEE PIPING WITH TEST ON ROOF TOP |
10/12/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
10/12/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
10/12/2005 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* |
10/17/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :*SOFFITS COMPLETE & ELEC ROOM |
10/17/2005 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* |
10/20/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
11/15/2005 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :*FIRE WRAP OK |
11/15/2005 | ELECTRIC - UNDERGROUND | RSUBA | Approved | IVRS - Inspection :*U.G BRANCH CIRCUITS SOUTH & EAST OR BUILDING |
11/16/2005 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :*NEED TO SEE COMPLETION OF WATER HEATER VENT PIPING, ALL APPLIANCE INSTALLED WITH SAFETY CABLES & FLEXES ATTACHED AND BOND POSTED FOR GAS CLEARANCE CARD. |
11/16/2005 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
11/17/2005 | BUILDING - PROGRESS | LHANLY | Approved | IVRS - Inspection :* |
11/18/2005 | MECHANICAL - PROGRESS | CWILLIAM | Approved | IVRS - Inspection :* |
11/21/2005 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
11/21/2005 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
11/21/2005 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
11/21/2005 | ELECTRIC - PROGRESS | RSUBA | Approved | IVRS - Inspection :* |
11/21/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO |
11/23/2005 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :*OK FOR TEMP C OF O |
11/23/2005 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :*RECEIVED LETTER FROM ENGINEER APPROVED SUPPLY BACKFLOW CERTIFICATIONS |
11/23/2005 | ENGINEERING - FINAL | NKALAHAR | Approved | BUILDING HAS NO CONCERNS AT THIS TIME AP WILL BE GIVEN WHEN GRADING WORK COMPLETED |
11/25/2005 | FIRE - FINAL | LLAKEY | Approved | |
11/25/2005 | FIRE - KITCHEN EXH HOOD FINAL | LLAKEY | Approved | |
11/25/2005 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
11/28/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*OK FOR FINAL C OF O |
11/28/2005 | HEALTH DEPT - FINAL 724-7908 | LMOSS | Approved | PER INSP |
11/28/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :*BUILDING INSPECTOR TO RECEIVE (1) BACKFLOW CERTIFICATION FOR CARBONATOR. RECEIVED (1) CARBONATOR + (3) DOUBLE CHECK ASSEMBLY BACKFLOW CERTIFICATIONS. |
11/28/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
12/12/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | |
02/01/2006 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
02/23/2006 | PERMIT FINALED | LJACKSON | Approved |