Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
01/20/2005
Applicant:
N/A
Description:
TI:RETAIL
Contractors:
  • DONAHUE CONSTRUCTION CORPORATION

Permit Reviews

Permit Number - T05CM00254
Permit Status: C of o
Permit Description: TI:RETAIL
Start Date Submittal Complete Date Status  
01/20/2005 PLANS OK TO SUBMIT - 3RD PARTY 01/21/2005 COMPLETED Review Details
01/21/2005 3RD PARTY REVIEW-COMMERCIAL 03/02/2005 COMPLETED Review Details
03/02/2005 POST 3RD PARTY REVIEW 03/10/2005 COMPLETED Review Details
03/11/2005 RESUBMITTAL 04/21/2005 COMPLETED Review Details
07/08/2005 3RD PARTY REVIEW-REVISION/OTHER 07/08/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM00254
Permit Status: C of o
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 1
Date Name
01/20/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM00254
Permit Description: TI:RETAIL
Total Completed Inspections - 22
Date Description Inspector Results Comments
05/24/2005 FRAMING LHANLY Approved IVRS - Inspection :*
05/31/2005 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*
06/15/2005 ELECTRIC - PROGRESS RSUBA Approved IVRS - Inspection :*
06/20/2005 ELECTRIC - TEMPORARY SERVICE RSUBA Approved IVRS - Inspection :* OK TO CLEAR FUEL & TEST POWER. W/BOND POSTED . BOND HAS BEEN POSTED
06/21/2005 TEP CLEARANCE - AM JKOZUCH Approved ECO
06/27/2005 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
06/28/2005 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :* OK FOR CEILING TILES. LEAVE OUT UNDER EACH DUCT SMOKE DETECTOR FOR FINAL TEST. NEED ACCESS PANELS IN HARD LIDS. WILL CHECK DRYER VENT T-TOP ON FINAL
06/28/2005 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
1) CALL IN FOR CLOSET RINGS PRIORT TO SETTING STOOLS
06/28/2005 ELECTRIC - INTERMEDIATE RSUBA Approved IVRS - Inspection :*
07/11/2005 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL C OF O
07/11/2005 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :* RECEIVED LETTER ?? COLD WATER PIPING INSULATION. (1) PROVIDE LISTGIN FOR SHAMPOO SINK VACUUM BREAKER FOR WATER SUPPLY
07/11/2005 PLUMBING - PROGRESS RRICH Approved IVRS - Inspection :*
07/11/2005 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
07/11/2005 ELECTRIC - UNDERGROUND RSUBA Approved IVRS - Inspection :*
07/11/2005 ELECTRIC - UFER RSUBA Approved IVRS - Inspection :*
07/11/2005 ELECTRIC - FINAL RSUBA Approved IVRS - Inspection :*
07/12/2005 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
07/12/2005 FIRE - FINAL LTHOMAS Approved
07/12/2005 FIRE SPKLR - FINAL LTHOMAS Approved
07/13/2005 BUILDING - FINAL LHANLY Approved
07/14/2005 PERMIT FINALED LJACKSON Approved
07/14/2005 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*WINDOW SIGNS REMOVED; NO ADD'L SIGNS AT THIS TIME