Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Address NEW:
7500 E GOLF LINKS RD
Apply Date:
09/19/2005
Applicant:
N/A
Description:
GRADING:3000CY CUT 4000CY FILL
Contractors:
  • FAR WEST CONSTRUCTION CORPORATIO

Permit Reviews

Permit Number - T05BU02323
Permit Status: Final
Permit Description: GRADING:3000CY CUT 4000CY FILL
Start Date Submittal Complete Date Status  
05/09/2006 RESUBMITTAL - GRADING 06/06/2006 COMPLETED Review Details
07/10/2006 RESUBMITTAL - GRADING 03/15/2007 COMPLETED Review Details
09/19/2005 PLANS OK TO SUBMIT - GRADING 09/23/2005 COMPLETED Review Details
09/23/2005 GRADING 11/08/2005 COMPLETED Review Details
10/02/2009 REVISION - GRADING 10/14/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05BU02323
Permit Status: Final
Permit Description: GRADING:3000CY CUT 4000CY FILL
Total Outstanding Activity Conditions - 1
Date Name
09/19/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T05BU02323
Permit Description: GRADING:3000CY CUT 4000CY FILL
Total Completed Inspections - 7
Date Description Inspector Results Comments
12/20/2006 STORMWATER INSTALL OF CONTROLS NKALAHAR Approved NO WORK STARTED YET
08/15/2007 ENGINEERING PRE-CONSTRUCTION NKALAHAR Approved MET WITH GORDON-HE WILL BE ACTING AS PM 971-6796

THIS PROJECT WILL BE SEMI PHASED
GORDON TO CALL WHEN CONTROLS IN PLACE
11/15/2007 GRADING - INTERMEDIATE NKALAHAR Approved SUBGRADE HAS BEEN SET
CURBING IN PLACE
PAVING SHOULD BE COMPLETE IN ABOUT 2 WEEKS
RIP RAP WORK ALMOST COMPLETED IN DRAINAGE ON EAST SIDE OF SITE
11/30/2007 STORMWATER FOLLOW-UP INSP NKALAHAR Approved ASPHALT HAS BEEN PLACED
GRADING WORK TO START ON SECOND PART OF LOT AND FOOTERS BEING DUG
03/30/2010 GRADING - FINAL DROBERTS Approved THE SITE APPEARS TO HAVE BEEN COMPLETED PER THE APPROVED PLANS. IT HAS BEEN NOTED THAT THE GATES ON THE TRASH ENCLOSURE HAS NOT BEEN PROVIDED AT THIS TIME, BUT ARE ON ORDER AND WILL BE INSTALLED PRIOR TO THE FINAL LANDSCAPE INSPECTION. I WILL WORK WITH ANDREW CONNOR ON THE LANDSCAPE APPROVAL AND WILL ENSURE THAT THE GATES ARE INSTALLED PRIOR TO THE APPROVAL OF THIS INSPECTION.
06/08/2010 LANDSCAPE INSPECTION DROBERTS Approved MODIFICATIONS TO THE SITE HAVE BEEN APPROVED BY JOSEPH LINVILLE FOR THIS SITE ON MAY 24, 2010. THE APPROVED COPY OF THE PLAN CAN BE FOUND IN SIRE AS A REVISION FOR PERMIT #T06CM06162.
10/25/2010 PERMIT FINALED DROBERTS Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW
None GRADING PLANS VIEW