Permit: T04CM04695
Permit Details
Apply Date:
10/22/2004
Applicant:
METRO PERMIT EXPRESS, INC
Description:
TI:DIALYSIS CENTER
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T04CM04695
Permit Status: C of o
Permit Description: TI:DIALYSIS CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/22/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 10/22/2004 | COMPLETED |
10/22/2004 | 3RD PARTY REVIEW-COMMERCIAL TI | 11/22/2004 | COMPLETED |
11/10/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 11/17/2005 | COMPLETED |
11/22/2004 | POST 3RD PARTY REVIEW | 07/26/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM04695
Permit Status: C of o
Permit Description: TI:DIALYSIS CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/22/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM04695
Permit Description: TI:DIALYSIS CENTER
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/15/2005 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
09/23/2005 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
09/23/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
09/23/2005 | ENGINEERING - FINAL | MRUSSO | Approved | |
09/23/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
09/25/2005 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
11/17/2005 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | 3RD FLOOR COMPLETE EXCEPT ROOM # 3126 4TH FLOOR NOT READY FOR INSPECTION |
11/17/2005 | MEDICAL - GAS/TEST INTERMED | RMYERS | Approved | ALL MEDICAL GAS PIPING TO MAINTAIN INTERIOR PURITY- BE SURE AND CAP ALL PIPING!! |
11/21/2005 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
11/28/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :* |
12/02/2005 | PLUMBING - INTERMEDIATE | RMYERS | Approved | N/H DWV,IN WALLS , AND OVERHEAD TO P.O.C OK COPPER IN WALLS OK OK TO INSULATE HOT. DIALYSIS DRAINS MAY NOT BE COMBINED |
12/06/2005 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :*PARTIAL R.O INSPECTION TO OVERHEAD |
12/14/2005 | PLUMBING - MEDICAL GAS/FINAL | RMYERS | Approved | IVRS - Inspection :*PIPING INTO THE ZONE MEDICAL AIR OXYGEN VACUUM |
12/20/2005 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* OK TO COVER ELECTRICAL IN CEILINGS OF PHASE "2A" AFTER CORRECTIONS ARE MADE. 1. SLACK WIRES TO GO TO CEILING 2. CLOSE UP ALL J-BOXES 3. ADD EXIT LIGHT IN HALL 4. MAKE SURE ALL LIGHTING WHIPS ARE ALL THE WAY IN THEIR CONNECTOR. |
12/27/2005 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :*OK TEMP C OF O ROOMS # 4101-H,I1,I2,J,L,M,N CORRIDOR Y |
12/28/2005 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :*CONTRACTOR REQUREST PARTIAL TEMP C OF O FOR ROOMS # 4101-H,I-1,I-2,J,L, M & N ALSO CORRIDOR Y. THESE AREAS ARE COMPLETE. CONTRACTOR WILL BUILD TEMPORARY CONTAINMENT WALL BETWEEN COMPLETED AND UNFINISHED WORK. |
12/30/2005 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :*PHASE II OK |
12/30/2005 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
12/30/2005 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
12/30/2005 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
12/30/2005 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* |
12/30/2005 | FIRE - FINAL | LTHOMAS | Approved | |
01/30/2006 | PERMIT FINALED | GBONILLA | Approved |