Permit: T04CM04695

Parcel: 11615088L

Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T04CM04695

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
01/20/2006 PLUMBING - FINAL Approved IVRS - Inspection :*PLUMBING FINAL OK
OK FOR C OF O PENDING ANY OTHER INSPECTION
01/17/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
1. COMPLETE ALL DRAINS IN MECHANICAL ROOM
12/28/2005 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*CONTRACTOR REQUREST PARTIAL TEMP C OF O FOR ROOMS # 4101-H,I-1,I-2,J,L, M & N ALSO CORRIDOR Y. THESE AREAS ARE COMPLETE. CONTRACTOR WILL BUILD TEMPORARY CONTAINMENT WALL BETWEEN COMPLETED AND UNFINISHED WORK.
09/22/2005 PLUMBING - FINAL Partial Approval IVRS - Inspection :*
1) PHASE ONE FINAL OK
ALL REQUIRED INSPECTIONS LEFT OPEN FOR PHASE TWO
OK FOR TEMP C OF O PHASE ONE ONLY
STOI
09/21/2005 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*