Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T04CM01908
Permit Details
Apply Date:
04/29/2004
Applicant:
METRO PERMIT EXPRESS
Description:
TI:RESTAURANT
Architects:
- GARCIA DAVID V
Contractors:
- SUNG S CONSTRUCTION L L C
Permit Reviews
Permit Number - T04CM01908
Permit Status: C of o
Permit Description: TI:RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/29/2004 | COMMERCIAL TI | 05/12/2004 | COMPLETED |
05/12/2004 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/15/2004 | COMPLETED |
06/15/2004 | POST 3RD PARTY REVIEW | 07/06/2004 | COMPLETED |
07/15/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 07/15/2004 | COMPLETED |
10/27/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 10/28/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM01908
Permit Status: C of o
Permit Description: TI:RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/29/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM01908
Permit Description: TI:RESTAURANT
Total Completed Inspections - 35
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/20/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection :*OK TO COVER |
07/20/2004 | PLUMBING - SEWER HCS CONNECT | JSTANLEY | Approved | IVRS - Inspection :* |
08/05/2004 | PLUMBING - ABOVE CEILING | JSTANLEY | Approved | IVRS - Inspection :* |
08/19/2004 | FRAMING | RSUBA | Approved | IVRS - Inspection :* NEED 3RD PARTY REVIEW APPROVAL OR CHANGE (HAVE STAMPED & SIGNED AT FINAL) |
08/31/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
09/08/2004 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :*/OK FOR CEILING TILES. LEAVE OUT AROUND HOOD |
09/16/2004 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :*/INSPECTED FIRE WRAP. OK FOR CEILING TILES |
09/20/2004 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :*/ 1) OK TEMP POWER FOR TEST SUBJECT TO BOND |
09/23/2004 | TEP CLEARANCE - PM | JKOZUCH | Approved | ECO PER LISA LESNY |
10/04/2004 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
10/04/2004 | MECHANICAL - HOOD SYSTEMS | JMILITEL | Approved | IVRS - Inspection :* |
10/06/2004 | FIRE - KITCHEN EXH HOOD FINAL | LLAKEY | Approved | |
10/06/2004 | FIRE - FINAL | LLAKEY | Approved | |
10/06/2004 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
10/07/2004 | ENGINEERING - FINAL | JSALINE | Approved | C OF O APPROVED. |
10/07/2004 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
11/01/2004 | HEALTH DEPT - FINAL 724-7908 | RPAYTON | Approved | |
11/01/2004 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :*/OK PER R. HOLANDER 11/1/04 |
11/01/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*/1)PLBG FINAL IS OK 2)OK FOR C/O |
11/01/2004 | BUILDING - PROGRESS | RSUBA | Approved | IVRS - Inspection :* |
11/01/2004 | SIGN - FINAL | RDEAR | Approved | IVRS - Inspection :* |
11/02/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*/OK FOR FINAL C/O. OK BLDG. FINAL AS PER BOB SUBA |
11/02/2004 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | |
11/02/2004 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | |
11/02/2004 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | |
11/02/2004 | PLUMBING - PROGRESS | TRINIVJR | Approved | |
11/02/2004 | ELECTRIC - UNDERGROUND | RSUBA | Approved | |
11/02/2004 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | |
11/02/2004 | ELECTRIC - PROGRESS | RSUBA | Approved | |
11/02/2004 | BUILDING - FINAL | RSUBA | Approved | |
11/02/2004 | BUILDING ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* |
11/02/2004 | SHEET ROCK NAILING | RSUBA | Approved | IVRS - Inspection :* |
11/02/2004 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
11/02/2004 | PLUMBING - GAS PRESS TEST FNL | TRINIVJR | Approved | IVRS - Inspection :* |
11/03/2004 | PERMIT FINALED | BGRANT | Approved |