Permit: T04CM00146
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
9565 E 22ND ST #105
Address NEW:
9565 E 22ND ST #105
Apply Date:
01/14/2004
Applicant:
N/A
Description:
TI:ICE CREAM SHOP- OK FOR TEMP C OF O PER BOB SUBA
Architects:
- LARRY CLICK
Contractors:
- EDEN BUILDERS INC ,
Permit Reviews
Permit Number - T04CM00146
Permit Status: C of o
Permit Description: TI:ICE CREAM SHOP- OK FOR TEMP C OF O PER BOB SUBA
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2004 | COMMERCIAL TI | 01/28/2004 | COMPLETED |
| 01/28/2004 | COMMERCIAL TI | 01/29/2004 | COMPLETED |
| 01/29/2004 | OTHER | 02/11/2004 | COMPLETED |
| 03/31/2004 | REVISION | 03/31/2004 | COMPLETED |
| 05/05/2004 | REVISION | 05/05/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM00146
Permit Status: C of o
Permit Description: TI:ICE CREAM SHOP- OK FOR TEMP C OF O PER BOB SUBA
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/14/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM00146
Permit Description: TI:ICE CREAM SHOP- OK FOR TEMP C OF O PER BOB SUBA
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2004 | MECHANICAL - PROGRESS | JMILITEL | Approved | IVRS - Inspection 0000*/ INSPECTED CONDENSATE DRAIN LINES, SUPPLY AND EXHAUST IN RESTROOM. REPAIR DAMAGED EXHAUST AT ROOF PENETRATION. OK FOR SHEET ROCK. INSPECTED SUSPENDED ROUGH DUCT. EXISTING A/C UNIT HAS A DUCT SMOKE DETECTOR. PROVIDE DIRECTION FROM ENGINEER OR SHELL CONTRACTOR IF NEW A/C IS REQUIRED TO HAVE ONE. |
| 04/01/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000* |
| 04/01/2004 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection 0000* |
| 04/01/2004 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection 0000* |
| 04/01/2004 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 04/02/2004 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
| 04/05/2004 | ELECTRIC - INTERMEDIATE | JORTA | Approved | IVRS - Inspection 0000* |
| 04/20/2004 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*/ 1) OK FOR CEILING TILES |
| 04/23/2004 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
| 04/29/2004 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :*/ CORRECTIONS MADE. TWO INTERIOR BACKFLOW CERTIFICATIONS TURNED IN. |
| 04/29/2004 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
| 04/29/2004 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 04/30/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 05/03/2004 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | IVRS - Inspection : See detailed listing on site.| 999*. APPROVED. |
| 05/03/2004 | BUILDING - TEMP POWER FOR TEST | LHANLY | Approved | IVRS - Inspection :* |
| 05/04/2004 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/04/2004 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/04/2004 | PLUMBING - TEMP POWER FOR TEST | RRICH | Approved | THIS JOB IS FINALED LEERAY SIGNED CARD |
| 05/04/2004 | TEP CLEARANCE - PM | JKOZUCH | Approved | ECO SENT TO TEP ON 05/04/04 |
| 05/04/2004 | ELECTRIC - TEMP POWER FOR TEST | JORTA | Approved | TESTING ONLY-NOT FOR OCCUPANCY. MOST ACCURATELY WIRE PANEL SCHEDULE AND NEW LOADS |
| 05/06/2004 | ENGINEERING - FINAL | JSALINE | Approved | C OF O APPROVED. |
| 05/07/2004 | HEALTH DEPT - FINAL 724-7908 | DTHOMAS | Approved | |
| 05/07/2004 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 05/07/2004 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | |
| 05/07/2004 | BUILDING - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 05/10/2004 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 05/10/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/02/2004 | PERMIT FINALED | RSUBA | Approved | |
| 07/02/2004 | RIGHT OF WAY - FINAL | RLEIGH | Approved |