GRADING:999 CY CUT/12,210 CY FILL
Contractors:
  • BOBRU CONSTRUCTION L L C

Permit Reviews

Permit Number - T04BU03026
Permit Status: Final
Permit Description: GRADING:999 CY CUT/12,210 CY FILL
Start Date Submittal Complete Date Status  
03/11/2005 RESUBMITTAL - GRADING ALL 04/11/2005 COMPLETED Review Details
05/04/2005 RESUBMITTAL - GRADING ALL 06/07/2005 COMPLETED Review Details
12/21/2004 PLANS OK TO SUBMIT - GRADING 12/22/2004 COMPLETED Review Details
12/22/2004 GRADING 02/03/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04BU03026
Permit Status: Final
Permit Description: GRADING:999 CY CUT/12,210 CY FILL
Total Outstanding Activity Conditions - 1
Date Name
12/21/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T04BU03026
Permit Description: GRADING:999 CY CUT/12,210 CY FILL
Total Completed Inspections - 8
Date Description Inspector Results Comments
06/08/2005 NPPO PRE PERMIT INSPECTION ACONNOR Approved
06/16/2005 ENGINEERING PRE-CONSTRUCTION MRUSSO Approved PERFORMED STORM WATER PRE-CONSTRUCTION MEETING.
BOB NESSINGER ( YARBUROUGH DEVELOPMENT)
MEL RITTER ( OWNER)
AND DAVID BUCKLAND (SUB-CONTRACTOR) IN ATTENDENCE
06/29/2005 STORMWATER INSTALL OF CONTROLS MRUSSO Approved 1) ROCK IS ON SITE FOR STABILIZED CONSTRUCTION ENTRANCE, ENSURE IT IS INSTALLED PER PLAN (SWPPP), TO MINIMIZE TRACKING OF SOIL OFF SITE.
2) SHOW ANY CHANGES TO YOUR SWPPP ON THE PLAN AND DOCUMENT THE DATE IS WAS DONE.
3) POST YOUR AZPDES AUTHORIZATION NUMBER AND/OR YOUR NOI ON SITE.
4) ESTABLISH A DESIGNATED CONCRETE WASH OUT AREA PER YOUR SWPPP.
5) PERFORM STORM WATER/ SEDIMENT CONTROLS MAINTENANCE INSPECTIONS AS CALLED FOR IN YOU R APPROVED SWPPP AND DOCUMENT THEM.
6) PERIODIC FOLLOW-UP INSPECTIONS WILL BE EPRFORMED AS NEEDED.
12/09/2008 GRADING - INTERMEDIATE MRUSSO Approved
12/17/2010 GRADING - FINAL DROBERTS Approved THE SITE WAS CHECKED TO SEE IF IT WAS READY FOR THE RELEASE OF THE GRADING PERMIT BUT HAS BEEN FOUND TO BE INCOMPLETE IN THE FOLLOWING AREAS: 1) MINOR CRACKS HAVE BEEN NOTED IN THE SIDEWALKS AT VARIOUS LOCATIONS THROUGHOUT THE SITE. IN THE CURRENT CONDITION SOME OF THESE MAY BE ACCEPTABLE AT THE FINAL INSPECTION AS LONG AS THERE IS NO MOVEMENT NOTED IN THE CRACK. 2) DAMAGED WHEELCHAIR ACCESS RAMPS HAVE BEEN NOTED AT THE FOLLOWING LOCATIONS AND MAY/WILL NEED TO BE REPLACED PRIOR TO THE FINAL RELEASE OF THE GRADING RESEEDING BOND AND CLOSING THIS PERMIT. THEY EITHER NEED TO BE DONE COMPLETELY BY REMOVING THE ENTIRE RAMP OR AN ACCEPTABLE DOWELING METHOD NEEDS TO BE UTILIZED TO PREVENT THE REPAIR AREAS FROM MOVING IN THE FUTURE. CONSULT THE ENGINEER OF RECORD FOR RECOMMENDATIONS FOR THESE TYPES OF REPAIRS. THE LOCATIONS ARE AS FOLLOWS, ADJACENT TO LOTS 1, 5, 6, 14, 18. 3) SIDEWALK HAS NOT BEEN CONSTRUCTED ADJACENT TO LOTS #8 THRU #13. AND LOTS 16 AND 17, A COMPLETION BOND WILL BE REQUIRED TO PLACE AGAINST THE ASSURANCES FOR S04-102. CURRENTLY THE PERMIT IS IN AN EXPIRED STATUS AND WILL NEED TO BEE PLACED BACK INTO AN ISSUED STATUS. CONTACT CLAUDIA BUFORD AT 791-5550 SO THAT SHE CAN ASSIST YOU WITH THE RE-ISSUANCE OF THIS GRADING PERMIT. IF YOU HAVE ANY QUESTIONS PLEASE FEEL FREE TO CONTACT ME, DAVID ROBERTS AT 349-7643 AND I WILL TRY TO ASSIST YOU AS MUCH AS POSSIBLE.
12/17/2010 LANDSCAPE INSPECTION DROBERTS Approved IT APPEARS AT THIS TIME THAT ALL OF THE LANDSCAPING MATERIAL HAS BEEN PROVIDED AS APPROVED PER THE APPROVED PLAN. THIS INSPECTION WILL BE RECHECKED PRIOR TO THE FINAL RELEASE TO ENSURE THAT THE PLANTS HAVE NOT BEEN CHANGED DURING THE COMPLETION OF THE PROJECT. ANY CHANGES WILL RESULT INTO THE INSTALLATION OF ADDITIONAL MATERIALS FOR THIS SITE.
12/17/2010 STORMWATER FINAL INSPECTION DROBERTS Approved THIS INSPECTION WILL NOT BE COMPLETED UNTILL ALL OF THE WORK IS EITHER COMPLETE OR THE SITE IS FULLY STABALIZED AS RECOMMENDED AND APPROVED BY THE ENGINEERING AND LANDSCAPING DEPARTMENTS.
12/17/2010 STORMWATER FOLLOW-UP INSP DROBERTS Approved MINOR CONCERNS AT THIS TIME ARE THE AREAS OF MINOR STANDING WATER IN THE SOUTH NUOS AREA DUE TO A CLOGGED DRAIN PIPE UNDERNEATH THE DECOMPOSED PATH AND SEDIMENT NOTED IN THE BASIN LOCATED AT THE NORTHWEST CORNER OF THIS SITE AND ADJACENT TO THE DRAINAGE INLET STRUCTURE FROM THE ROADWAY. THIS MATERIAL NEEDS TO BE REMOVED AS MUCH AS POSSIBLE TO ENSURE POSITIVE DRAINAGE IS CONTINUALLY MAINTAINED. THIS BASIN WILL BE CHECKED DURING THE NEXT 1/2 INCH RAIN EVENT TO SEE IF IT IS DRAINING CORRECTLY PER OUR CURRENT STANDARDS. IF IT IS TAKING LONGER THAN 12 HOUR TO DRAIN FREELY YOU WILL BE REQUIRED TO SEEK AN INSPECTION AND RECOMMENDATIONS FROM THE ENGINEER OF RECORD ON HOW TO RECTIFY THE PROBLEM.