Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4066 N ORACLE RD
Address NEW:
4066 N ORACLE RD
Apply Date:
12/22/2003
Applicant:
METRO PERMIT EXPRESS, INC
Description:
TI:BEAUTY SCHOOL
Architects:
  • ALLEVA, ANSELMO FRANCISCO
Contractors:
  • RIO WEST DEVELOPMENT AND CONSTRU

Permit Reviews

Permit Number - T03CM05851
Permit Status: C of o
Permit Description: TI:BEAUTY SCHOOL
Start Date Submittal Complete Date Status  
01/15/2004 RESUBMITTAL 01/28/2004 COMPLETED Review Details
03/02/2004 3RD PARTY REVIEW-REVISION/OTHER 03/08/2004 COMPLETED Review Details
03/26/2004 3RD PARTY REVIEW-REVISION/OTHER-2ND 04/05/2004 COMPLETED Review Details
05/14/2004 3RD PARTY REVIEW-REVISION/OTHER 05/24/2004 COMPLETED Review Details
12/22/2003 PLANS OK TO SUBMIT - 3RD PARTY 12/23/2003 COMPLETED Review Details
12/23/2003 3RD PARTY REVIEW-COMMERCIAL 01/15/2004 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T03CM05851
Permit Status: C of o
Permit Description: TI:BEAUTY SCHOOL
Total Outstanding Activity Conditions - 1
Date Name
12/22/2003 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T03CM05851
Permit Description: TI:BEAUTY SCHOOL
Total Completed Inspections - 28
Date Description Inspector Results Comments
01/28/2004 FIRE SPKLR - FINAL LTHOMAS Approved
04/01/2004 ELECTRIC - INTERMEDIATE RMAJUTA Approved IVRS - Inspection 0000*/ 1) APPROVED WALLS
04/07/2004 MECHANICAL - PROGRESS CWILLIAM Approved IVRS - Inspection 0000*/ 1) DRYER VENT IN WALL OK. ABOVE PLATE, TERMINATE WITH 2"X4" INTO LARGER FLASHING OR TRANSITION 2½X4" INTO 4" CENTERLINE AND TERMINATE INTO 4" FLASH. 2) ALL SUPPLY/RETURN DUCT ABOVE CEILING GRID NEEDS TO BE WRAPPED WITH 3/4" DUCT WRAP WHEN LOCATED UNDER BLDG INSULATION. 3) AREA ABOVE CEILING GRID DOES NOT QUALIFY AS PLENIUM, R.A. ONLY PLENIUM RATED MATERIAL QUILIFIES
04/13/2004 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection 0000*
04/19/2004 SHEET ROCK NAILING RSUBA Approved IVRS - Inspection 0000*
04/20/2004 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection 0000*
05/10/2004 MECHANICAL - ABOVE CEILING CWILLIAM Approved IVRS - Inspection :*
05/10/2004 MECHANICAL - INTERMEDIATE CWILLIAM Approved IVRS - Inspection :*
05/13/2004 ELECTRIC - ABOVE CEILING MCAPISTR Approved IVRS - Inspection :*
05/13/2004 BUILDING ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
05/13/2004 FRAMING AQUIROZ Approved IVRS - Inspection :*
05/20/2004 FIRE - FINAL LLAKEY Approved
05/20/2004 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*/ CLOSET FLANGES OK. OK TO COVER ALL AREAS.
05/20/2004 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
05/24/2004 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
05/25/2004 PLUMBING - GAS PRESS TEST FNL RMYERS Approved IVRS - Inspection :*
05/25/2004 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection :*/ 1) CONTRACTOR - VERY IMPORTANT NOT TO COVER OR CONCEAL PIPING BEFORE INSP. - THIS INCLUDES PAINTING PIPE. 2) PRESSURE TEST OK. PIPING OK. NOT PER PLAN - BUT IS ALL VISIBLE AND MEETS BTU AND LENGTH SPECS ON PLAN. 3) OK TO COVER.
05/26/2004 ELECTRIC - FINAL RMAJUTA Approved IVRS - Inspection :* THE REVISED DRAWING WAS ON SITE. THE SUBJECT ELECTRICAL SERVICES ARE ENERGIZED AND IN SERVICE
05/26/2004 RIGHT OF WAY - FINAL LLOPEZ Approved
05/26/2004 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*/ 1) PLBG FINAL OK. 2) OK FOR C OF O PENDING ANY OTHER INSP.
05/26/2004 ELECTRIC - PROGRESS RMAJUTA Approved
05/27/2004 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
07/08/2004 TEP CLEARANCE - PM JKOZUCH Approved
08/02/2004 ENGINEERING - FINAL JSALINE Approved C OF O APPROVED.
08/10/2004 TEP CLEARANCE - AM JKOZUCH Approved
09/13/2004 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
09/17/2004 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*/ 1) OK C OF O
09/20/2004 PERMIT FINALED JWEATHER Approved