Permit: T03CM03722
Permit Details
Apply Date:
07/25/2003
Applicant:
RHL DESIGN GROUP INC
Description:
NEW:DRUG STORE
Contractors:
- DAMITIO CONSTRUCTION INC ,
Permit Reviews
Permit Number - T03CM03722
Permit Status: C of o
Permit Description: NEW:DRUG STORE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/16/2004 | 3RD PARTY REVIEW-REVISION/OTHER | 03/26/2004 | COMPLETED |
07/25/2003 | PLANS OK TO SUBMIT - COMM | 07/25/2003 | COMPLETED |
07/25/2003 | PLANS OK TO SUBMIT - SITE | 07/25/2003 | COMPLETED |
07/25/2003 | SITE | 09/15/2003 | COMPLETED |
07/31/2003 | 3RD PARTY REVIEW-COMMERCIAL | 08/21/2003 | COMPLETED |
09/10/2003 | 3RD PARTY REVIEW-COMMERCIAL | 10/06/2003 | COMPLETED |
09/15/2003 | RESUBMITTAL - SITE | 10/08/2003 | COMPLETED |
10/06/2003 | RESUBMITTAL | 10/17/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM03722
Permit Status: C of o
Permit Description: NEW:DRUG STORE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/25/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM03722
Permit Description: NEW:DRUG STORE
Total Completed Inspections - 40
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/19/2003 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000*/ 3/0 BARE STRANDED CU. TO REBAR AT N.W CORNER OF FOUNDATION |
11/19/2003 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* EXCLUDES SITE WALL |
12/02/2003 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000*/ 1) PVC DWV UNDERGROUND OK. 2) WATER TEST ONE RISER TO TEN FEET. 3) OK TO BACKFILL. |
12/02/2003 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection 0000* |
12/15/2003 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*/ YARD WTR STUBBED UNDER SLAB AND UP INSIDE BLDG OK. PRESSURE TEST OK. OK TO COVER. |
12/15/2003 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* ON BUILDING ONLY |
12/22/2003 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* 4' 8" LIFT SITE WALL NORTH SIDE |
12/31/2003 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000*/ SITE LIGHTING AND SIGN POWER UNDERGROUND PVC. |
01/06/2004 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
01/09/2004 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
01/26/2004 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*/ 1) PVC DWV THRU ROOF OK. WTR TEST OK. 2) COPPER OK. CLOSET FLANGES OK. 3) OK TO COVER ALL AREAS. |
02/03/2004 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
02/11/2004 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection 0000* |
02/13/2004 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
02/13/2004 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
03/03/2004 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000*/ OK TO COVER GRID. |
03/03/2004 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000*/ ABOVE CEILING OK. |
03/03/2004 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
03/05/2004 | ELECTRIC - ABOVE CEILING | MCAPISTR | Approved | IVRS - Inspection 0000* |
03/10/2004 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
03/10/2004 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | |
03/10/2004 | ELECTRIC - TEMP POWER FOR TEST | MCAPISTR | Approved | |
03/10/2004 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | IVRS - Inspection 0000* |
03/10/2004 | BUILDING - TEMP POWER FOR TEST | AQUIROZ | Approved | |
03/15/2004 | TEP CLEARANCE - PM | JKOZUCH | Approved | |
03/25/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
03/25/2004 | FIRE - FINAL | LTHOMAS | Approved | |
03/25/2004 | FIRE SPKLR - FINAL | LTHOMAS | Approved | 1) OK C OF O |
03/26/2004 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
04/06/2004 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
04/06/2004 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection 0000* |
04/13/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/13/2004 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
04/13/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
04/16/2004 | ENGINEERING - FINAL | JBRUCKME | Approved | |
05/13/2004 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :*/ 1) CORRECTIONS MADE OK. PLBG FINAL OK. 2) OK FOR C OF O PENDING ANY OTHER INSP. |
05/13/2004 | OUTDOOR LIGHTING FINAL | MCAPISTR | Approved | IVRS - Inspection :* |
05/13/2004 | BUILDING - FINAL | AQUIROZ | Approved | OK FOR C/O |
06/24/2004 | PERMIT FINALED | RLEIGH | Approved | |
06/24/2004 | RIGHT OF WAY - FINAL | RLEIGH | Approved |