Permit: T03CM01865
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
4225 E FAIRMOUNT ST #05
Address NEW:
4225 E FAIRMOUNT ST #05
Apply Date:
04/16/2003
Applicant:
INTEGRATED DESIGN & CONSTRUCTION
Description:
NEW:TRIPLEX
Architects:
- AMY, NORMAN ARTHUR
Contractors:
- INTEGRATED DESIGN AND CONSTRUCTI
Permit Reviews
Permit Number - T03CM01865
Permit Status: C of o
Permit Description: NEW:TRIPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/25/2004 | 3RD PARTY REVIEW-RESIDENTIAL | 04/12/2004 | COMPLETED |
| 04/12/2004 | RESUBMITTAL | 05/24/2004 | COMPLETED |
| 04/16/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 04/28/2003 | COMPLETED |
| 04/16/2003 | PLANS OK TO SUBMIT - SITE | 04/21/2003 | COMPLETED |
| 04/28/2003 | SITE | 06/16/2003 | COMPLETED |
| 04/29/2003 | 3RD PARTY REVIEW-COMMERCIAL | 05/13/2003 | COMPLETED |
| 05/31/2006 | REVISION - SITE | 06/05/2006 | COMPLETED |
| 06/23/2003 | RESUBMITTAL - SITE | 04/12/2004 | COMPLETED |
| 12/28/2005 | PLANS OK TO SUBMIT - SITE | 12/28/2005 | COMPLETED |
| 12/28/2005 | REVISION - SITE | 05/31/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM01865
Permit Status: C of o
Permit Description: NEW:TRIPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/16/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM01865
Permit Description: NEW:TRIPLEX
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/21/2004 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | IVRS - Inspection :* 1) INTERIOR SLAB OK TO POUR 2) F3 FOOTING NOT IN 3) PATIO/PORCH SLABS NOT READY |
| 12/21/2004 | BUILDING PRE-SLAB | BSTEVENS | Approved | IVRS - Inspection :* |
| 12/22/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection :*/WRAP OK PROVIDE LETTER ON FLAT VENTED UNITS OR PLAN |
| 12/27/2004 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK #2 TO REBAR |
| 01/26/2005 | ROOF NAILING | BSTEVENS | Approved | IVRS - Inspection :*PROVIDE PROOF THAT F3 FOOTING WERE INSTALLED PER PLAN |
| 01/26/2005 | EXT METAL CLIPS/EXT SHEATHING | BSTEVENS | Approved | IVRS - Inspection :* |
| 05/17/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/20/2005 | FRAMING | BSTEVENS | Approved | IVRS - Inspection :* |
| 05/27/2005 | SHEET ROCK NAILING | BSTEVENS | Approved | IVRS - Inspection :* |
| 08/01/2005 | REINFORCED MASONRY PRE-GROUT | HLEYVA | Approved | |
| 08/23/2005 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* 1) OK CABLE DROP ONLY-NO POWER-CEC |
| 08/23/2005 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection :* 1) SOIL WATER TEST IS OK 2) HCS CONNECTION IS OK 3) OK TO BACKFILL TRENCH |
| 08/29/2005 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection :* 1) YARD WATER LINE FROM METER TO BLDG SERVICE IS OK |
| 11/23/2005 | ELECTRIC - CONSTRUCTION POWER | RSUBA | Approved | IVRS - Inspection :* |
| 11/25/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | TEMP CONST POWER |
| 12/04/2005 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | IVRS - Inspection :* |
| 12/07/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 12/07/2005 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection :*PLBG FINAL IS OK OK FOR C OF O |
| 12/07/2005 | PLUMBING - BACK WATER VALVE | TRINIVJR | Approved | IVRS - Inspection :* |
| 12/07/2005 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | IVRS - Inspection :* |
| 12/07/2005 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection :* |
| 12/14/2005 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection :* |
| 12/22/2005 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/22/2005 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 12/23/2005 | BUILDING - FINAL | JCAGLE | Approved | IVRS - Inspection :* |
| 12/27/2005 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 12/27/2005 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 12/27/2005 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 12/29/2005 | ENGINEERING - FINAL | JBRUCKME | Approved | TEMPORARY C OF O APPROVED - POST BOND 1. COMPLETE SITE DRAINAGE AND ROCK RIP RAP. 2. WIDEN DRIVEWAY DRIVEWAY TO A MINIMUM OF 20' AND PROVIDE CURB. 3. PROVIDE A C.O.T. APPROVED SITE PLAN SHOWING ALL MODIFICATIONS. |
| 12/29/2005 | NPPO - FINAL | ACONNOR | Approved | OK for Temp. C of O For approval complete landscape per plan: 1) 10' landscape border along Fairmount St. 2) 5' wall to screen V.U.A from residential property to the West. 3) Mitigation for NPPO plants. |
| 12/29/2005 | LANDSCAPE - FINAL | ACONNOR | Approved | OK for Temp. C of O For approval complete landscape per plan: 1) 10' landscape border along Fairmount. 2) 5' wall to screen V.U.A from residential property to the West. 3) Mitigation for NPPO plants. |
| 12/13/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
| 12/13/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | |
| 12/13/2006 | BUILDING ABOVE CEILING | LHANLY | Approved | |
| 12/13/2006 | STUCCO MESH | LHANLY | Approved | |
| 12/13/2006 | U VALUE FOR WINDOW | LHANLY | Approved | |
| 12/13/2006 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | |
| 12/13/2006 | ELECTRIC - INTERMEDIATE | RMAJUTA | Approved | |
| 12/13/2006 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | |
| 12/13/2006 | ELECTRIC - TEMPORARY POLE | RMAJUTA | Approved | |
| 12/13/2006 | ELECTRIC - TEMPORARY SERVICE | RMAJUTA | Approved | |
| 01/31/2007 | PERMIT FINALED | LJACKSON | Approved |