Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/01/2006 | ENGINEERING - FINAL | Approved | Project approved | |
| 12/29/2005 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED - POST BOND 1. COMPLETE SITE DRAINAGE AND ROCK RIP RAP. 2. WIDEN DRIVEWAY DRIVEWAY TO A MINIMUM OF 20' AND PROVIDE CURB. 3. PROVIDE A C.O.T. APPROVED SITE PLAN SHOWING ALL MODIFICATIONS. |
|
| 12/27/2005 | ENGINEERING - FINAL | Denied | THERE IS NO GRADING PERMIT OR PLAN FOR THIS SITE. SEE NOTICE PLACED BY PAUL MACHADO ON 5-24-04 REQUIRING A GRADING PLAN SUBMITTAL 1. PROVIDE A C.O.T. APPROVED GRADING PLAN. 2. PROVIDE A C.O.T. APPROVED SITE PLAN SHOWING ALL MODIFICATIONS. 3. PROVIDE DRAINAGE AND DRIVEWAY WIDTHS PER THE APPROVED PLANS. |