Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4790 S JULIAN AV
Address NEW:
4790 S JULIAN AV
Apply Date:
01/31/2003
Applicant:
TAYLOR, ROBERT JOHN
Description:
TI:OFFICE & MFG TEMP C OF O PER STEVE LONG
Architects:
  • TAYLOR, ROBERT JOHN
Contractors:
  • TL ROOF AND ASSOCIATES

Permit Reviews

Permit Number - T03CM00507
Permit Status: C of o
Permit Description: TI:OFFICE & MFG TEMP C OF O PER STEVE LONG
Start Date Submittal Complete Date Status  
01/31/2003 3RD PARTY REVIEW-COMMERCIAL TI 03/07/2003 COMPLETED Review Details
01/31/2003 PLANS OK TO SUBMIT - COMM 01/31/2003 COMPLETED Review Details
01/31/2003 SITE 03/07/2003 COMPLETED Review Details
04/21/2003 3RD PARTY REVIEW-REVISION/OTHER 04/28/2003 COMPLETED Review Details
04/30/2003 3RD PARTY REVIEW-REVISION/OTHER 05/06/2003 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T03CM00507
Permit Description: TI:OFFICE & MFG TEMP C OF O PER STEVE LONG
Total Completed Inspections - 31
Date Description Inspector Results Comments
03/10/2003 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK
2.) P.O.C. OF NEW BLDG. DRAIN TO EXSISTING BLDG. DRAIN IS OK
3.) OK TO BACKFILL TRENCH.
03/10/2003 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection 0000*
03/27/2003 FRAMING LHANLY Approved IVRS - Inspection 0000*
03/31/2003 ROOF NAILING LHANLY Approved IVRS - Inspection 0000*
03/31/2003 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved IVRS - Inspection 0000*
03/31/2003 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection 0000*
04/01/2003 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection 0000*
1.) ABS DWV THRU ROOF OK
2.) COPPER IN WALLS OK PLEASE ALLOW PLUMBER TIME TO INSULATE HOT LINE BEFORE SHEET ROCK.
3.) CLOSET FLANGES OK
4.) OK TO COVER WALLS.
04/01/2003 U VALUE FOR WINDOW LHANLY Approved IVRS - Inspection 0000*
04/03/2003 ELECTRIC - INTERMEDIATE JORTA Approved IVRS - Inspection 0000*
04/08/2003 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection 0000*
04/17/2003 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection 0000*
04/17/2003 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection 0000*
04/22/2003 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection 0000*OK FOR CEILING TILES.
04/22/2003 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection 0000*ABOVE CEILING IS OK FOR GRID & TILE.
04/22/2003 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection 0000*
04/24/2003 PLUMBING - FINAL TRINIVJR Approved PLBG. FINAL IS OK
OK FOR C OF O.
04/28/2003 ELECTRIC - UFER JORTA Approved IVRS - Inspection 0000*
05/02/2003 FIRE - FINAL JEGAN Approved IVRS - Inspection 0000*
05/02/2003 FIRE SPKLR - FINAL JEGAN Approved IVRS - Inspection 0000*
05/02/2003 PLUMBING - YARD WTR LINE/TEST TRINIVJR Approved 1.) ALL CORRECTIONS HAVE BEEN MADE.
2.) OK FOR C OF O.
05/05/2003 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection 0000*OK FOR C OF O.
05/05/2003 MECHANICAL - INTERMEDIATE JMILITEL Approved
05/05/2003 RIGHT OF WAY - FINAL LLOPEZ Approved
05/05/2003 SIGN - FINAL JYBARRA Approved NO SIGN AT THIS TIME
05/05/2003 OUTDOOR LIGHTING FINAL MCAPISTR Approved IVRS - Inspection 0000*
05/05/2003 ELECTRIC - CABLE DROP MCAPISTR Approved IVRS - Inspection 0000*SENT TO TEP ON 5/6/03 AT 9:15AM OK FOR TEMP C OF O. PENDING VERIFICATION OF BONDING OF BLDG. STEEL, SPRINKLER PIPE, & GAS PIPING TO ELECTRIC SERVICE.
05/06/2003 LANDSCAPE - FINAL PGILBERT Approved
05/07/2003 ELECTRIC - FINAL JORTA Approved IVRS - Inspection 0000*WILL CALL T.E.P.
05/07/2003 ELECTRIC - UNDERGROUND JORTA Approved
05/16/2003 BUILDING - FINAL LHANLY Approved IVRS - Inspection 0000*OK C OF O.
08/08/2003 ENGINEERING - FINAL JBRUCKME Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW
None CONSTRPLANS VIEW
TEMP C OF O_05-06-2003.TIF CERT OF OCC VIEW
C OF O_07-07-2004.TIF CERT OF OCC VIEW