Permit: T02CM05302
Permit Details
Apply Date:
11/15/2002
Applicant:
WALD-HOPKINS, WILLIAM DAVID
Description:
NEW:ACTIVITY CENTER
Architects:
- WALD-HOPKINS, WILLIAM DAVID
Contractors:
- HEERY INTERNATIONAL INC ,
- PACIFIC BUILDING INTERIORS INC ,
Permit Reviews
Permit Number - T02CM05302
Permit Status: C of o
Permit Description: NEW:ACTIVITY CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/21/2003 | RESUBMITTAL | 02/28/2003 | COMPLETED |
| 02/28/2003 | RESUBMITTAL | 04/15/2003 | COMPLETED |
| 11/15/2002 | COMMERCIAL NEW | 01/10/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM05302
Permit Status: C of o
Permit Description: NEW:ACTIVITY CENTER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/15/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM05302
Permit Description: NEW:ACTIVITY CENTER
Total Completed Inspections - 31
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2003 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection 0000* |
| 06/19/2003 | STEM WALL/RETAINING WALL | AMATHIES | Approved | IVRS - Inspection 0000* |
| 06/27/2003 | PLUMBING - ROUGH, SOIL | AQUIROZ | Approved | IVRS - Inspection 0000* |
| 07/07/2003 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
| 07/08/2003 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection 0000* |
| 09/25/2003 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 10/16/2003 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 11/07/2003 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection 0000*/ 1) ROOF DRAINS OK. 2) ABS DWV OK. 3) WATER OK. 4) OK TO COVER ALL AREAS. |
| 11/07/2003 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/07/2003 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000* |
| 11/14/2003 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection 0000*/ 1) OK HARD LID ACTIVITY ROOM. 2) OK WALLS ROUGH. |
| 11/14/2003 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | |
| 11/14/2003 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/09/2003 | STUCCO MESH | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/16/2003 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/30/2003 | PLUMBING - PROGRESS | TRINIVJR | Approved | IVRS - Inspection 0000*/ 1) GAS PRESSURE TEST IS OK. 2) NOTE: THIS INSPECTION IS FOR 1ΒΌ" GAS SERVICE FROM NEW METER LOCATION TO BLDG SERVICE AS RED LINED ON PLAN. 3) OK TO BACKFILL TRENCH. |
| 03/02/2004 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 03/25/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*/ PERMANENTLY LABEL DISCONNECTS WIUNIT NO. AND CIRCUIT NO. PROVIDE CHASE NIPPLES WHERE WIRES ENTER CABINET OF A/C UNIT WEST END. ELECTRICAL INSP.WILL FOLLOW UP ON CORRECTIONS. OK FOR FINAL C OF O. |
| 03/25/2004 | MECHANICAL - PROGRESS | JMILITEL | Approved | |
| 03/25/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 03/25/2004 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | |
| 03/26/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*/ PLBG FINAL IS OK. OK FOR C OF O. |
| 04/13/2004 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection 0000*/ LETTERS ON TORQUE AND J-BOX OK TO GO TO FILES. ALL ITEMS OF LAST INSP PER DAN S.C. CORRECTED. ALSO AC UNITS ON ROOF OK WITH LABELS AND BUSHINGS PER MECH INSP. |
| 04/14/2004 | PERMIT FINALED | AMATHIES | Approved | |
| 04/14/2004 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 05/10/2004 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 05/10/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 05/10/2004 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 05/10/2004 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection :* |
| 05/11/2004 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/11/2004 | FIRE SPKLR - FINAL | LTHOMAS | Approved | 1) OK FOR C OF O |