Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Apply Date:
08/26/2002
Applicant:
HAGEDON, BRIAN GEORGE
Description:
NEW:ADMINISTRATIVE BLDG
Architects:
  • HAGEDON, BRIAN GEORGE

Permit Reviews

Permit Number - T02CM04035
Permit Status: C of o
Permit Description: NEW:ADMINISTRATIVE BLDG
Start Date Submittal Complete Date Status  
05/16/2003 REVISION 06/06/2003 COMPLETED Review Details
06/03/2003 REVISION 06/03/2003 COMPLETED Review Details
07/08/2003 REVISION 07/15/2003 COMPLETED Review Details
08/26/2002 COMMERCIAL NEW 01/27/2003 COMPLETED Review Details
08/28/2002 COMMERCIAL NEW 04/03/2003 COMPLETED Review Details
10/28/2003 REVISION 10/28/2003 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T02CM04035
Permit Status: C of o
Permit Description: NEW:ADMINISTRATIVE BLDG
Total Outstanding Activity Conditions - 1
Date Name
08/26/2002 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T02CM04035
Permit Description: NEW:ADMINISTRATIVE BLDG
Total Completed Inspections - 40
Date Description Inspector Results Comments
05/01/2003 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection 0000*OK 20' COPPER IN FOOTING.
06/18/2003 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) P.O.C. OF NEW BLDG DRAIN TO EXISTING BLDG DRAIN AND SEWER IS OK 3) OK TO BACKFILL TRENCH
06/26/2003 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection 0000*
06/26/2003 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection 0000*
06/26/2003 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection 0000*
08/01/2003 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection 0000*
09/30/2003 ROOF NAILING LHANLY Approved IVRS - Inspection 0000*/ 1) PLEASE FINISH CLINCHING NAILS ON STRAPS
10/02/2003 PLUMBING - GAS PRESSURE TEST RRICH Approved IVRS - Inspection 0000*
10/02/2003 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection 0000*
10/02/2003 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection 0000*
10/14/2003 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection 0000*
10/14/2003 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection 0000*/ ALL CORRECTIONS MADE.
10/21/2003 EXT METAL CLIPS/EXT SHEATHING RSUBA Approved IVRS - Inspection 0000*
10/22/2003 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection 0000*
10/27/2003 STUCCO MESH LHANLY Approved IVRS - Inspection 0000*
11/13/2003 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection 0000*/ NEED TO SEE DUCT SMOKE DETECTOR, UNIT 8. PROVIDE MIN. 1" CLEARANCE FROM INSULATION AND COMBUSTABLES AROUND WATER HEATER VENT. PROVIDE AN EXPLANATION FROM YOUR ENGINEER WHY AC-7 HAS A DUCT SMOKE DETECTOR AND WHY IT IS IN THE SUPPLY DUCT. COMBUSTION AIR DUCTS IN WATER HEATER ROOM MUST BE SEPERATE UNTIL THEY GET TO THE ROOF. LEAVE OUT CEILING TILES IN AREAS TO BE REINSPECTED. WILL CHECK CORRECTIONS ON FINAL.
11/13/2003 BUILDING ABOVE CEILING AMATHIES Approved IVRS - Inspection 0000*
12/08/2003 MECHANICAL - TEMP PWR FOR TEST JMILITEL Approved IVRS - Inspection 0000*
12/08/2003 PLUMBING - TEMP POWER FOR TEST RRICH Approved IVRS - Inspection 0000*
12/08/2003 OUTDOOR LIGHTING FINAL JORTA Approved
12/08/2003 ELECTRIC - FINAL JORTA Approved IVRS - Inspection 0000*
12/08/2003 ELECTRIC - TEMP POWER FOR TEST JORTA Approved IVRS - Inspection 0000*/ TEMP POWER APPROVED. CHECKED WITH LEERAY - OK SUBJECT TO BOND.
12/08/2003 ELECTRIC - CONSTRUCTION POWER JORTA Approved IVRS - Inspection 0000*
12/08/2003 ELECTRIC - TEMPORARY SERVICE JORTA Approved IVRS - Inspection 0000*
12/08/2003 ELECTRIC - ABOVE CEILING JORTA Approved
12/08/2003 ELECTRIC - INTERMEDIATE JORTA Approved
12/08/2003 ELECTRIC - UNDERGROUND JORTA Approved
12/10/2003 BUILDING - TEMP POWER FOR TEST LHANLY Approved IVRS - Inspection 0000*
12/10/2003 FRAMING LHANLY Approved IVRS - Inspection 0000*
12/11/2003 PLUMBING - FINAL RRICH Approved IVRS - Inspection 0000*/ 2-BACKFLOW [RPB'S] REPORTS. 1-BACTERIA H20 REPORT.
12/11/2003 PLUMBING - PROGRESS RRICH Approved
12/11/2003 PLUMBING - SEWER HCS CONNECT RRICH Approved
12/16/2003 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection 0000*/ OK FOR C OF O. LEFT GAS CARD.
12/18/2003 NPPO - FINAL PGILBERT Approved
12/26/2003 RIGHT OF WAY - FINAL PWHIDDON Approved TEMP C OF O ONLY
12/26/2003 ENGINEERING - FINAL DROBERTS Approved TEMPORARY C OF O APPROVED AT THIS TIME, FINAL NOT TO BE GIVEN UNTIL ALL EXTERIOR IS COMPLETE
12/30/2003 FIRE - FINAL LTHOMAS Approved
12/30/2003 BUILDING - FINAL LHANLY Approved IVRS - Inspection 0000* OK FOR TEMP C/O STRUCUAL & EGRESS COMPLETE. NEED C/O FINALS
12/31/2003 SIGN - FINAL JYBARRA Approved
08/20/2004 PERMIT FINALED LHANLY Approved