Permit: T02CM03201
Permit Details
Apply Date:
07/05/2002
Applicant:
N/A
Description:
ADDITION:CLASSROOM BUILDING & REST ROOM
Contractors:
- L V H CONSTRUCTION INC ,
- HEERY INTERNATIONAL INC ,
Permit Reviews
Permit Number - T02CM03201
Permit Status: C of o
Permit Description: ADDITION:CLASSROOM BUILDING & REST ROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2003 | REVISION | 01/24/2003 | COMPLETED |
| 03/25/2003 | REVISION | 03/26/2003 | COMPLETED |
| 06/06/2003 | REVISION | 06/10/2003 | COMPLETED |
| 07/05/2002 | COMMERCIAL NEW | 10/28/2002 | COMPLETED |
| 07/05/2002 | SITE | 09/30/2002 | COMPLETED |
| 10/14/2002 | RESUBMITTAL | 11/12/2002 | COMPLETED |
| 10/14/2002 | RESUBMITTAL - SITE | 11/12/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM03201
Permit Status: C of o
Permit Description: ADDITION:CLASSROOM BUILDING & REST ROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/05/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM03201
Permit Description: ADDITION:CLASSROOM BUILDING & REST ROOM
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2002 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000*SENT TO TEP 11/18/02 AT 9:15AM OK TO CLEAR TEMP POLE.INSPECTION OF TEMP POLE OK OK TO CLEAR. |
| 12/06/2002 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 12/09/2002 | EXCAVATION/LAYOUT REBAR & ZON | HLEYVA | Approved | IVRS - Inspection 0000*OK NORTH WING AND BATHROOMS. |
| 12/17/2002 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000*SLAB DOWELLS LOCATED @ NORTH END OF BUILDING ONLY, PER ENGINEER NOTE DATED 12-9-02. |
| 12/19/2002 | ELECTRIC - UNDERGROUND | MCAPISTR | Approved | IVRS - Inspection 0000* 1.) SECONDARY PVC TFMR TO BLDG. 2.) PVC RUNS BETWEEN DIST. CENTER & BLDG. 400 3.) PVC FOR SPCL. SYSTEMS. |
| 12/30/2002 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0999*1.) WATER MAIN REQUIRES TWO FEET CLEAR BETWEEN SEWER AND WATER PIPING OR INSTALL DIP 6 FEE EITHER SIDE OF WATER MAIN. 2.) HCS TIE IN AT MAIN OK SADDLE TAP OK. 3.) OK TO COVER TO MIDDLE OF STREET. 4.) OK TO COVER FROM DIRECTIONAL CLEANOUT TO CURB. |
| 12/30/2002 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000* |
| 12/30/2002 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000* |
| 01/06/2003 | BUILDING PRE-SLAB | HLEYVA | Approved | IVRS - Inspection 0000* |
| 02/04/2003 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection 0000* 1.) TOP EAST WING, TOP NORTH WING. 2.) COMPLETING TOP OUT OF BATHROOMS DROP HORIZTONTAL AND OK TO GROUT. |
| 02/19/2003 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 03/18/2003 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection 0000* |
| 03/18/2003 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection 0000* |
| 03/18/2003 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection 0000*1.) ABS DWV THRU ROOF OK WATER TEST OK 2.) COPPER WATER TEST OK 3.) OK TO COVERK ALL AREAS. NOTE: YOU MAY NOT TERMINATE CONDENSATE WASTE INTO SINK TAILPIECE. |
| 03/21/2003 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 03/28/2003 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 03/28/2003 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 03/28/2003 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 04/14/2003 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 05/13/2003 | ELECTRIC - TEMP POWER FOR TEST | RMAJUTA | Approved | OK TO TEMP POWER FOR TESTING SUBJECT TO OTHER INSPECTORS. BOND NOT REQUIRED SCHOOL. |
| 05/13/2003 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | IVRS - Inspection 0000* |
| 05/14/2003 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000*CONDENSATE DRAINS RE ROUTED FROM SINK TO OUTSIDE 2.) YOU MAY WANT TO INCLUDE MECHANICAL INSPECTOR ON THIS INSPECTION CLEAN UP REQUIRE ACCESS AND CLEARANCE. |
| 05/14/2003 | BUILDING - TEMP POWER FOR TEST | AMATHIES | Approved | IVRS - Inspection 0000* |
| 05/15/2003 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 05/16/2003 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 05/19/2003 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 06/03/2003 | ELECTRIC - FINAL | JORTA | Approved | IVRS - Inspection 0000* |
| 06/24/2003 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
| 06/25/2003 | FIRE SPKLR - FINAL | LLACHY | Approved | |
| 06/25/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 07/14/2003 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection 0000*/ 1) YOU MUST HAVE ALL REQUIRED INSPECTIONS BEFORE CALLING FINAL. YARD PIPING OK 2) PLUMBING FINAL-OK 3) OK FOR C OF O PENDING ANY OTHER INSPECTIONS 4) DELTA FIVE GAS REVISION OK PRESSURE TEST OK 5) LAST INSPECTOR ON JOB TO LEAVE GAS CARD |
| 07/14/2003 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | |
| 07/14/2003 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000* |
| 07/15/2003 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection 0000*/ 1) PENDING ALL OTHER TRADES |
| 07/16/2003 | FIRE - FINAL | LLAKEY | Approved | |
| 07/16/2003 | OUTDOOR LIGHTING FINAL | JORTA | Approved | |
| 07/17/2003 | PERMIT FINALED | JYBARRA | Approved | |
| 07/17/2003 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 07/17/2003 | SIGN - FINAL | JYBARRA | Approved | |
| 07/17/2003 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 07/18/2003 | LANDSCAPE - FINAL | JLINVILL | Approved |