Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2003 | PLUMBING - PROGRESS | Approved | IVRS - Inspection 0000* | |
| 03/17/2003 | PLUMBING - PROGRESS | Not ready for Inspection | NOT READY FOR INSPECTION. | |
| 03/12/2003 | PLUMBING - PROGRESS | Not ready for Inspection | NOT READY FOR INSPECTION. | |
| 01/10/2003 | PLUMBING - PROGRESS | Partial Approval | 1.) SOIL WATER TEST IS OK 2.)P.O.C. OF NEW 2" WASTE FOR DRINKINS FOUNTAIN IS OK 3.) OK TO BACKFILL TRENCH. |
|
| 01/09/2003 | PLUMBING - PROGRESS | Denied | IVRS - Inspection 0999* 1.) CAN NOT HAVE A FLAT FACED BUSHING ON A HORIZONTAL POSITION 2.) MUST HAVE A 10' HEAD FOR WATER TEST 3.) MUST USE SPECIALTY COUPLING FOR FLOOR DRAIN 4.) WILL REQUIRE A REVISED & APPROVED PLAN AND CONNECTION FEES PAID FOR DRINKING FOUNTIAN. |