Permit: T01CM03755
Permit Details
Apply Date:
07/31/2001
Applicant:
N/A
Description:
NEW:AUTO BODY & PAINT
Architects:
- FENECK, JOHN
Contractors:
- C D ENTERPRISES
Permit Reviews
Permit Number - T01CM03755
Permit Status: C of o
Permit Description: NEW:AUTO BODY & PAINT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/18/2002 | REVISION | 04/24/2002 | COMPLETED |
| 10/23/2002 | REVISION | 11/13/2002 | COMPLETED |
| 12/10/2001 | 3RD PARTY REVIEW-COMMERCIAL | 02/13/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T01CM03755
Permit Status: C of o
Permit Description: NEW:AUTO BODY & PAINT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/31/2001 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM03755
Permit Description: NEW:AUTO BODY & PAINT
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/08/2002 | ELECTRIC - UFER | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 03/21/2002 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000* |
| 03/28/2002 | PLUMBING - ROUGH, SOIL | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 04/04/2002 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | IVRS - Inspection 0000*FLOOR BOXES IN OFFICES 3-3/4" RUNS IN REPAIR AREA. |
| 07/10/2002 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection 0000*MAIN BLD DONE. |
| 08/06/2002 | PLUMBING - GAS PRESSURE TEST | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 08/06/2002 | PLUMBING - ABOVE CEILING | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 08/06/2002 | PLUMBING - INTERMEDIATE | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 09/12/2002 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
| 09/12/2002 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/11/2002 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | IVRS - Inspection 0000* |
| 10/11/2002 | PLUMBING - TEMP POWER FOR TEST | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 10/11/2002 | ELECTRIC - TEMP POWER FOR TEST | MCAPISTR | Approved | IVRS - Inspection 0000*SENT TO TEP ON 10/14/02 AT 9:15 OK CLEAR TEMP POWER. |
| 10/11/2002 | BUILDING - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection 0000* |
| 10/16/2002 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/16/2002 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/17/2002 | MECHANICAL - FINAL | JMILITEL | Approved | |
| 10/17/2002 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 10/17/2002 | ELECTRIC - ABOVE CEILING | RMAJUTA | Approved | IVRS - Inspection 0000* |
| 10/17/2002 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection 0000* |
| 10/18/2002 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*OK FOR CEILING TILES. |
| 11/06/2002 | FIRE SPKLR - FINAL | JEGAN | Approved | |
| 11/12/2002 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 11/12/2002 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000*OKAY FOR C OF O. |
| 11/12/2002 | PLUMBING - FINAL | FMCCLURE | Approved | IVRS - Inspection 0000* |
| 11/12/2002 | PLUMBING - SEWER HCS CONNECT | FMCCLURE | Approved | |
| 11/12/2002 | PLUMBING - YARD WTR LINE/TEST | FMCCLURE | Approved | |
| 11/13/2002 | SIGN - FINAL | DJOHNSTO | Approved | |
| 11/15/2002 | LANDSCAPE - FINAL | PGILBERT | Approved | Clarify 5' screen wall requirement along Winsett Ave. Revise plan/site as necessary. |
| 11/15/2002 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 11/15/2002 | ELECTRIC - FINAL | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 11/15/2002 | ELECTRIC - TEMPORARY SERVICE | MCAPISTR | Approved | |
| 11/15/2002 | ELECTRIC - CABLE DROP | MCAPISTR | Approved | |
| 11/15/2002 | ELECTRIC - INTERMEDIATE | MCAPISTR | Approved | IVRS - Inspection 0000* |
| 11/15/2002 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000*1.) AS BUILTS SUBMITTED & APPROVED BY DSD. 2.) SPECIAL INSP. REPORTS ACCEPTED FOR FIELD WELDS AND H.S. BOLTING. |
| 11/15/2002 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
| 01/17/2003 | PERMIT FINALED | PGILBERT | Approved | |
| 01/24/2003 | FIRE SPKLR - OH PIPING & HYDRO | JEGAN | Approved | |
| 01/24/2003 | FIRE SPKLR - UG PIPING FLUSH | JEGAN | Approved | |
| 01/24/2003 | FIRE SPKLR - UG, PIPING, HYDRO | JEGAN | Approved |