Permit: DP22-0218
Permit Details
Status:
Complete
Type:
Development Package
Address:
1620 W VALENCIA RD
Address NEW:
1620 W VALENCIA RD
Apply Date:
08/08/2022
Applicant:
Brandy Burke
Description:
Site/Grading - Taco Bell Bocci Endeavor.
Permit Reviews
Permit Number - DP22-0218
Permit Status: Complete
Permit Description: Site/Grading - Taco Bell Bocci Endeavor.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/08/2022 | DEV PKG - OK TO SUBMIT | 08/15/2022 | COMPLETED |
| 08/15/2022 | DEV PKG | 09/15/2022 | COMPLETED |
| 01/22/2024 | AS-BUILT v.1 | 01/30/2024 | APPROVED |
| 02/07/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 03/23/2023 | REQUIRES RESUBMIT |
| 05/24/2023 | DEVELOPMENT PACKAGE NEW v.1 | 07/06/2023 | APPROVED |
| 04/18/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 05/18/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0218
Permite Description: Site/Grading - Taco Bell Bocci Endeavor.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2023 | COT - SITE - Zoning Intermediate | N/A | Not Ready | Met with MW Morrissey to look over some proposed changes that they are planning to make on this site. I have advised them that their Engineer of Records needs to meet with the Reviewers for Zoning and Engineering and get their Approval for the changes before they perform the work in the field. If the work is done before an Approval of the Revised Drawings is done then it could result in having to removed anything that is not Approved on the Revised drawings. |
| 10/17/2023 | ENGR - Drainage Structures | N/A | Partial Pass | NE trash enclosure all rebar and dobies in place okay to pour floor. |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0218
Permit Description: Site/Grading - Taco Bell Bocci Endeavor.
Total Completed Inspections - 20