Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP22-0193
Permit Details
Apply Date:
07/13/2022
Applicant:
Alicia Simmons
Description:
Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Permit Reviews
Permit Number - DP22-0193
Permit Status: Issued
Permit Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/13/2022 | DEV PKG - OK TO SUBMIT | 07/21/2022 | COMPLETED |
07/21/2022 | DEV PKG | 09/15/2022 | COMPLETED |
10/19/2023 | DEVELOPMENT PACKAGE NEW v.3 | 12/01/2023 | APPROVED |
07/19/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/24/2023 | REQUIRES RESUBMIT |
09/21/2023 | DEVELOPMENT PACKAGE NEW v.2 | 10/19/2023 | REQUIRES RESUBMIT |
12/15/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 07/14/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP22-0193
Permite Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/29/2023 | PDSD Site/Engineering Division - NPPO | N/A | Partial Pass | Completed Pre-Con meeting with Damion and went over Nursery located at SE corner of site (1) mesquite tree to be TOS and (1) to be PIP and (1) palo verde to be TOS. |
01/16/2024 | SITE - SWPPP Correction Notice | N/A | Partial Pass | The wattles are on place and the track-out rock in place too. |
01/16/2024 | COT - SITE - Zoning Intermediate | N/A | Partial Pass | Call tractor just broke ground, cutting the grade and the pad. And cutting the trench for storm drain. |
07/09/2024 | SITE - Stormwater Final Inspection | N/A | Partial Pass | contractor removed and replace a 32 inch CMP pipe. Contractors backfilling it was betting San up to Spring Lane and then using a bid to top it off with |
12/29/2023 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | Walked site with Damion all set up and controls are in place for site will call inspection every 2 weeks for follow up inspections. |
06/20/2024 | ENGR - Drainage Structures | N/A | Partial Pass | Contractors for me the HEADWALL for the 36 inch CMP East End of it. Good to pour. |
08/06/2024 | SITE - Stormwater Setup and Controls | N/A | Partial Pass | Need to finish all the basins and the water harvesting |
08/08/2024 | Consultation SITE | N/A | Partial Pass | Contractor is setting steel for the driveway and parking lot. Good to pour. |
06/20/2024 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time |
09/05/2024 | ENGR Engineering Final | N/A | Partial Pass | contractor needs to complete landscaping. There’s area in the landscaping where they placed riprap and no filter fabric. I need to remove the rip wrap and install filter fabric on the north side behind the wall contractor needs to clean up behind that wall. Contractor missing the grates on the east end of the building those need to be installed also good for level 4 T. C. O. |
01/16/2024 | ENGR Grading Final | N/A | Partial Pass | Contractors cutting the grade for the pads and the trench for the CMP pipe |
Completed Inspections
Permit Status: Issued
Permit Number: DP22-0193
Permit Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Total Completed Inspections - 13