Permit: DP22-0193
Permit Details
Status:
Complete
Type:
Development Package
Address:
7471 S HOUGHTON RD
Address NEW:
7471 S HOUGHTON RD
Apply Date:
07/13/2022
Applicant:
Description:
Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Permit Reviews
Permit Number - DP22-0193
Permit Status: Complete
Permit Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/13/2022 | DEV PKG - OK TO SUBMIT | 07/21/2022 | COMPLETED |
| 07/21/2022 | DEV PKG | 09/15/2022 | COMPLETED |
| 10/19/2023 | DEVELOPMENT PACKAGE NEW v.3 | 12/01/2023 | APPROVED |
| 07/19/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/24/2023 | REQUIRES RESUBMIT |
| 09/21/2023 | DEVELOPMENT PACKAGE NEW v.2 | 10/19/2023 | REQUIRES RESUBMIT |
| 12/15/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 07/14/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0193
Permite Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/29/2023 | PDSD Site/Engineering Division - NPPO | N/A | Partial Pass | Completed Pre-Con meeting with Damion and went over Nursery located at SE corner of site (1) mesquite tree to be TOS and (1) to be PIP and (1) palo verde to be TOS. |
| 01/16/2024 | SITE - SWPPP Correction Notice | N/A | Partial Pass | The wattles are on place and the track-out rock in place too. |
| 01/16/2024 | COT - SITE - Zoning Intermediate | N/A | Partial Pass | Call tractor just broke ground, cutting the grade and the pad. And cutting the trench for storm drain. |
| 07/09/2024 | SITE - Stormwater Final Inspection | N/A | Partial Pass | contractor removed and replace a 32 inch CMP pipe. Contractors backfilling it was betting San up to Spring Lane and then using a bid to top it off with |
| 12/29/2023 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | Walked site with Damion all set up and controls are in place for site will call inspection every 2 weeks for follow up inspections. |
| 06/20/2024 | ENGR - Drainage Structures | N/A | Partial Pass | Contractors for me the HEADWALL for the 36 inch CMP East End of it. Good to pour. |
| 08/06/2024 | SITE - Stormwater Setup and Controls | N/A | Partial Pass | Need to finish all the basins and the water harvesting |
| 06/20/2024 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time |
| 09/05/2024 | ENGR Engineering Final | N/A | Partial Pass | contractor needs to complete landscaping. There’s area in the landscaping where they placed riprap and no filter fabric. I need to remove the rip wrap and install filter fabric on the north side behind the wall contractor needs to clean up behind that wall. Contractor missing the grates on the east end of the building those need to be installed also good for level 4 T. C. O. |
| 01/16/2024 | ENGR Grading Final | N/A | Partial Pass | Contractors cutting the grade for the pads and the trench for the CMP pipe |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0193
Permit Description: Site/Grading/Swppp - Mister Car Wash. New car wash with associated parking/drainage/utilities.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/15/2024 | COT - SITE - Zoning Intermediate | Passed | Are the easement and special conditions are good | |
| 02/15/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | important contractor to call him every two weeks for stormwater follow up and to maintain the track out rock and the wattles. | |
| 08/06/2024 | ENGR - Drainage Structures | Passed | ||
| 08/06/2024 | SITE - Zoning Final | Passed | ||
| 08/06/2024 | SITE - Zoning Compliance | Passed | ||
| 08/06/2024 | NPPO Pre-Construction | Passed | ||
| 08/06/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | ||
| 08/08/2024 | Consultation SITE | Passed | Contractor is setting steel for the driveway and parking lot. Good to pour. | |
| 09/12/2024 | ENGR Engineering Final | Passed | All items requested have been completed, CO ready | |
| 09/12/2024 | SITE | Passed | ||
| 09/12/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 09/12/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 09/12/2024 | ENGR Grading Final | Passed | ||
| 09/12/2024 | Verify required native plant protection, relocation, removal is completed prior to activity on job site | Passed | ||
| 02/05/2025 | COT - ENGR - Signage Final | Passed |