Inspection Status: Partial Pass
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/16/2024 |
ENGR Grading Final |
|
Partial Pass |
Contractors cutting the grade for the pads and the trench for the CMP pipe |
| 02/15/2024 |
ENGR Grading Final |
|
Not Ready |
Contractors don’t work it on the grading they’re working on installations of the 36 inch CMP pipe on the south end of the building |
| 03/04/2024 |
ENGR Grading Final |
|
Partial Pass |
Contractors, continuing to grade for the building and for the parking lot |
| 07/01/2024 |
ENGR Grading Final |
|
Partial Pass |
Contractor needs to submit plans for the roof. Drain changes. |
| 09/12/2024 |
ENGR Grading Final |
|
Passed |
|