Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Grading Final
Permit Number - DP22-0193
Inspection Description - ENGR Grading Final
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2024 | ENGR Grading Final | Partial Pass | Contractors cutting the grade for the pads and the trench for the CMP pipe | |
| 02/15/2024 | ENGR Grading Final | Not Ready | Contractors don’t work it on the grading they’re working on installations of the 36 inch CMP pipe on the south end of the building | |
| 03/04/2024 | ENGR Grading Final | Partial Pass | Contractors, continuing to grade for the building and for the parking lot | |
| 07/01/2024 | ENGR Grading Final | Partial Pass | Contractor needs to submit plans for the roof. Drain changes. | |
| 09/12/2024 | ENGR Grading Final | Passed |