Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - ENGR - Stormwater
Permit Number - DP22-0193
Inspection Description - COT - ENGR - Stormwater
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2024 | COT - ENGR - Stormwater | Not Ready | Contractors using a rain day too wet to work out here | |
| 02/15/2024 | COT - ENGR - Stormwater | Partial Pass | Contractor is working on the 36 inch CMP pipe south end of the building five rows | |
| 03/04/2024 | COT - ENGR - Stormwater | Complete (Recurring) | contractor installed five rows of CMP pipe 300 lineal feet on the south west corner going east | |
| 05/09/2024 | COT - ENGR - Stormwater | Partial Pass | No concerns at this time. Everything looks good. | |
| 07/09/2024 | COT - ENGR - Stormwater | Partial Pass | contractor removed 36 inch CMP because of the damage. Replaced it with new CMP backfilling deal with Pattinson and top it off with .AB | |
| 12/29/2023 | COT - ENGR - Stormwater | Complete (Recurring) | Walked site with Damion all set up and controls are in place for site will call inspection every 2 weeks for follow up inspections. |