Permit Details

Status:
Issued
Type:
Development Package
Apply Date:
05/30/2022
Applicant:
Description:
Site/Grading/Swppp - Mueller Inc.

Permit Reviews

Permit Number - DP22-0147
Permit Status: Issued
Permit Description: Site/Grading/Swppp - Mueller Inc.
Start Date Submittal Complete Date Status  
05/30/2022 DEV PKG - OK TO SUBMIT 06/15/2022 COMPLETED Review Details
06/15/2022 DEV PKG 09/05/2022 COMPLETED Review Details
01/17/2023 DEVELOPMENT PACKAGE REVIEW v.2 01/23/2023 REQUIRES RESUBMIT Review Details
01/23/2023 DEVELOPMENT PACKAGE REVIEW v.3 06/07/2023 REQUIRES RESUBMIT Review Details
06/26/2023 DEVELOPMENT PACKAGE NEW v.1 07/10/2023 REQUIRES RESUBMIT Review Details
08/14/2023 DEVELOPMENT PACKAGE NEW v.3 09/14/2023 APPROVED Review Details
07/28/2023 DEVELOPMENT PACKAGE NEW v.2 08/02/2023 REQUIRES RESUBMIT Review Details
12/06/2022 DEVELOPMENT PACKAGE REVIEW v.1 12/21/2022 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP22-0147
Permite Description: Site/Grading/Swppp - Mueller Inc.
Total Outstanding Inspections - 7
Last Inspection Date Description Inspector Results Comments
03/05/2024 ENGR Engineering Final N/A Not Ready
03/07/2024 ENGR Grading Final N/A Not Ready
05/09/2024 SITE - Stormwater Final Inspection N/A Complete (Recurring) Everything looks good at this time. Reschedule for STORMWATER in two weeks.
05/29/2024 PDSD Site/Engineering Division - NPPO N/A Complete (Recurring) Storm water follow up
10/17/2024 COT - BASN - Drainage/Basin - Condition Inspection N/A Complete (Recurring) Basins are cut and still in production. Channels into the basins are being formed, drainage pipe is in place, head walls still need to be installed.
09/24/2024 SITE - Stormwater Follow-up N/A Complete (Recurring) No Concerns at this time. The contractor is working in the basement installing pipe that goes out to the right away. All other other portions of the site is in compliance.
04/25/2024 ENGR - Drainage Structures N/A Partial Pass This inspection was for trash enclosure walls, we cannot pass this inspection unless engineer on record gives us a certified letter stating rebar and grout are completed per plan. Slab still needs to be seen prior to pouring.

Completed Inspections

Permit Status: Issued
Permit Number: DP22-0147
Permit Description: Site/Grading/Swppp - Mueller Inc.
Total Completed Inspections - 5
Date Description Inspector Results Comments
02/28/2024 SITE - Zoning Final Passed
01/16/2024 PDSD Engineering Division Pre-Construction SITE Passed
10/23/2024 ENGR - Drainage Structures Passed
11/01/2024 Consultation SITE Passed wall footing. okay to pour
11/08/2024 For trash and recycling enclosures Passed

Documents

File Name Document Type  
APPROVED_4_PLAN SET_MC_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
APPROVED_4_PLAN SET_MC_V1.PDF DOCUMENTS VIEW
2_DP COMMENT RESPONSE_V1.PDF DOCUMENTS VIEW
2_DP PLAN SET_V1.PDF DOCUMENTS VIEW
2_GEOTECH_V1.PDF DOCUMENTS VIEW
2_DP COMMENT RESPONSE_V1.PDF DOCUMENTS VIEW
2_GEOTECH_V1.PDF DOCUMENTS VIEW
1_CIVIL PLAN SET, 33 PAGES, 06.03.22.PDF PLANS UNDER REVIEW VIEW
1_ONLINE SUBMITTAL APPLICATION, RECVD 05.23.22.PDF PLANS UNDER REVIEW VIEW