Permit: DP21-0193
Permit Details
Apply Date:
07/28/2021
Applicant:
Lisa Bowers
Description:
Tentative Plat - My Place at the Landing. new hotel.
Permit Reviews
Permit Number - DP21-0193
Permit Status: Complete
Permit Description: Tentative Plat - My Place at the Landing. new hotel.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/28/2021 | DEV PKG - OK TO SUBMIT | 08/04/2021 | COMPLETED |
08/04/2021 | TENTATIVE PLAT REVIEW | 09/22/2021 | COMPLETED |
11/04/2021 | TENTATIVE PLAT REVIEW | 12/17/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0193
Permite Description: Tentative Plat - My Place at the Landing. new hotel.
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 10/17/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/ NO CONCERNS AT IS TIME} ; {Activity date: 09/14/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN / TRACK OUT ROCK IS GOOD AND THE WATTLES ARE TOO .INFORMED THE CONTRACTOR TO CALL IN INSPECTION EVERY TWO WEEKS.} |
10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
09/26/2023 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | Work in progress |
09/26/2023 | SITE - SWPPP Violation Notice | N/A | Not Ready | Work in progress |
09/26/2023 | SITE - SWPPP Correction Notice | N/A | Not Ready | Work in progress |
09/26/2023 | SITE - Stormwater Setup and Controls | N/A | Not Ready | Work in progress |
09/25/2023 | SITE - Stormwater Final Inspection | N/A | Complete (Recurring) | Contractor needs to finish the riprap |
09/26/2023 | ENGR Engineering Final | N/A | Not Ready | Work in progress |
09/25/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | Contractor still working on putting in plants and riprap |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0193
Permit Description: Tentative Plat - My Place at the Landing. new hotel.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/10/2023 | COT - ENGR - Signage Final | Passed | ||
10/11/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
10/11/2023 | SITE - SWPPP Violation Notice | Passed | ||
10/11/2023 | SITE - SWPPP Correction Notice | Passed | ||
10/13/2023 | SITE - Stormwater Setup and Controls | Passed | ||
10/20/2023 | SITE - Stormwater Final Inspection | Passed | ||
11/21/2023 | ENGR Engineering Final | Passed | ||
11/21/2023 | ENGR Grading Final | Passed | ||
11/21/2023 | PDSD Site/Engineering Division - Landscaping | Passed |