Permit: DP21-0193

Parcel: 13705557A

Inspection Status: Not Ready

Inspection History: PDSD Site/Engineering Division - Landscaping

Permit Number - DP21-0193

Inspection Description - PDSD Site/Engineering Division - Landscaping

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 PDSD Site/Engineering Division - Landscaping Not Ready
10/27/2022 PDSD Site/Engineering Division - Landscaping Not Ready
09/25/2023 PDSD Site/Engineering Division - Landscaping Partial Pass Contractor still working on putting in plants and riprap
09/26/2023 PDSD Site/Engineering Division - Landscaping Not Ready Work in progress
10/09/2023 PDSD Site/Engineering Division - Landscaping Passed 1) Good count on plants, landscape looks great.
10/11/2023 PDSD Site/Engineering Division - Landscaping Partial Pass Rip Rap is completed all hand placed with filter fabric installed in all rip rap areas, all trees do not have stake poles will need to verify prior to recall of inspection.

All trees, plants, and shrubs are completed and are well irrigated.
10/13/2023 PDSD Site/Engineering Division - Landscaping Partial Pass Walked site with Superintendent Henry regarding the West reaper parking lot drainage issue regarding the depression needed per plan to retain drainage and he will have grading and landscape contractors review on site and adjust prior to recall of inspection.
10/20/2023 PDSD Site/Engineering Division - Landscaping Partial Pass TC of O level 4 is granted for occupancy of building pending remaining landscape items to be completed.

General clean up is needed for sidewalk from West parking lot to the Santa Cruz pavement walkway.

Bollards on West side of parking lot need missing caps and (2) need to be reset in concrete they are not secure and are leaning.

Tree stakes need to be completed and dead trees need to be replaced.

SE parking lot drainage areas will need to be dug down to a depth of 9” below curb cut inlet and landscaping adjusted to achieve storm water containment from parking lot runoff.
11/21/2023 PDSD Site/Engineering Division - Landscaping Passed