Permit Details

Status:
Issued
Type:
Development Package
Address:
4206 N LULU CT
Address NEW:
4206 N LULU CT
Apply Date:
06/23/2021
Applicant:
Description:
Rev 1 started 10.17.2025 - adding gate ** Grading/ Swppp - Limberlost Estates, Lots 1 through 10 and common areas.

Permit Reviews

Permit Number - DP21-0163
Permit Status: Issued
Permit Description: Rev 1 started 10.17.2025 - adding gate ** Grading/ Swppp - Limberlost Estates, Lots 1 through 10 and common areas.
Start Date Submittal Complete Date Status  
06/23/2021 DEV PKG - OK TO SUBMIT (GRADING ONLY) 07/01/2021 COMPLETED Review Details
07/01/2021 GRADING 08/30/2021 COMPLETED Review Details
10/17/2025 DEVELOPMENT PACKAGE NEW REVISION v.1 11/06/2025 REQUIRES RESUBMIT Review Details
06/27/2023 DEVELOPMENT PACKAGE REVIEW v.1 07/18/2023 REQUIRES RESUBMIT Review Details
08/21/2023 DEVELOPMENT PACKAGE NEW v.1 09/20/2023 APPROVED Review Details
11/19/2025 DEVELOPMENT PACKAGE NEW REVISION v.2 11/20/2025 APPROVED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP21-0163
Permite Description: Rev 1 started 10.17.2025 - adding gate ** Grading/ Swppp - Limberlost Estates, Lots 1 through 10 and common areas.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
05/30/2024 PDSD Site/Engineering Division - NPPO N/A Not Applicable
05/30/2024 ENGR - Drainage Structures N/A Not Applicable
05/29/2024 SITE - Stormwater Follow-up N/A Partial Pass
11/05/2024 SITE - Stormwater Final Inspection N/A Partial Pass Contractors got finished with the basins yet
10/13/2025 ENGR Grading Final N/A Partial Pass contractor needs to submit the changes from the vertical curb to wedge curb

Completed Inspections

Permit Status: Issued
Permit Number: DP21-0163
Permit Description: Rev 1 started 10.17.2025 - adding gate ** Grading/ Swppp - Limberlost Estates, Lots 1 through 10 and common areas.
Total Completed Inspections - 9
Date Description Inspector Results Comments
04/25/2024 Verify required native plant protection, relocation, removal is completed prior to activity on job site Passed
04/25/2024 PDSD Engineering Division Pre-Construction SITE Passed superintendent Lance at 975-2730, Bryan with desert earth excavating. 10 unit subdivision with 10 parking spaces, a trash enclosure and a large basin.
None of the native trees are shown to remain.
Post address. Schedule regular swppp inspections. Provide controls at Northwest basin opening into grocery store parking lot. Schedule inspection prior to landscaping.
05/29/2024 SITE - Stormwater Setup and Controls Passed
05/29/2024 NPPO Pre-Construction Passed
03/26/2025 COT - ENGR - Site - Assurance Release Passed
10/13/2025 COT - ENGR - Stormwater Passed
10/13/2025 SITE - Stormwater Final Inspection Passed
07/13/2026 ENGR Engineering Final Passed
07/13/2026 ENGR Grading Final Passed