Permit: DP21-0111
Permit Details
Apply Date:
04/27/2021
Applicant:
Description:
Site/Grading/Swppp - Tucson Airport DC (TADC-C), new shell building.
Permit Reviews
Permit Number - DP21-0111
Permit Status: Complete
Permit Description: Site/Grading/Swppp - Tucson Airport DC (TADC-C), new shell building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/27/2021 | DEV PKG - OK TO SUBMIT | 05/05/2021 | COMPLETED |
| 05/05/2021 | DEV PKG | 06/10/2021 | COMPLETED |
| 07/15/2021 | DEV PKG - RESUBMITTAL | 08/30/2021 | COMPLETED |
| 09/06/2021 | DEV PKG - RESUBMITTAL | 09/08/2021 | COMPLETED |
| 09/27/2021 | DEV PKG - RESUBMITTAL | 10/14/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0111
Permite Description: Site/Grading/Swppp - Tucson Airport DC (TADC-C), new shell building.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/24/2021 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 11/24/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN/ PRE CON. WAS DONE BY DAVE ROBERTS 9185 (GRADING - INTERMEDIATE) CN .SURVEY ON SITE .} ; {Activity date: 11/24/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN 3350 E MEDINA RD} |
| 01/19/2022 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | {Activity date: 01/19/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /HAVE NOT STARTED INSTALLING THE STORMWATER YET. 3350 E MEDINA RD} ; {Activity date: 01/19/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /HAVE NOT STARTED INSTALLING THE STORMWATER YET 6715 S LISA FRANK AV} |
| 06/01/2022 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 06/01/2022; Status: Continued; Inspector: MERNANDEZ; Comment: Entered by VVERA1 - CN / GOOD} ; {Activity date: 05/04/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/ NO CONCERNS } ; {Activity date: 03/03/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /NEED TO CALL EVERY TWO WEEKS FOR INSPECTION.} ; {Activity date: 02/25/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - CONTINUED, NO CONCERNS AT THIS TIME, 3350 E Medina Rd} |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0111
Permit Description: Site/Grading/Swppp - Tucson Airport DC (TADC-C), new shell building.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2023 | SITE - SWPPP Correction Notice | Passed | N/A | |
| 01/27/2023 | SITE - Stormwater Final Inspection | Passed | N/A | |
| 01/27/2023 | COT - ENGR - Signage Final | Passed | N/A | |
| 01/27/2023 | PDSD Site/Engineering Division - NPPO | Passed | N/A | |
| 01/27/2023 | SITE - SWPPP Violation Notice | Passed | N/A | |
| 03/10/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 03/10/2023 | ENGR Grading Final | Passed | ||
| 03/10/2023 | ENGR Engineering Final | Passed |