Permit Number - DP21-0108
Permit Status: Complete
Permit Description: Site/Grading/Swppp - Popeye's Louisiana Kitchen. New restaurant.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/22/2021 | DEV PKG - OK TO SUBMIT | 04/28/2021 | COMPLETED |
| 04/28/2021 | DEV PKG | 06/16/2021 | COMPLETED |
| 07/07/2021 | DEV PKG - RESUBMITTAL | 09/01/2021 | COMPLETED |
| 09/20/2021 | DEV PKG - RESUBMITTAL | 10/21/2021 | COMPLETED |
| 11/02/2021 | DEV PKG - RESUBMITTAL | 11/15/2021 | COMPLETED |
| 12/27/2022 | DEVELOPMENT PACKAGE REVIEW v.2 | 01/30/2023 | APPROVED |
| 12/01/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/08/2022 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP21-0108
Permite Description: Site/Grading/Swppp - Popeye's Louisiana Kitchen. New restaurant.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 09/22/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN / INFORMED THE CONTRACTOR TO CALL IN FOR INSPECTION EVERY TWO WEEKS.} ; {Activity date: 09/21/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/ INFORMED THE CONTRACTOR TO CALL IN FOR INSPECTION EVERY TWO WEEKS. TRACK OUT ROCK IN PLACE .WATTLES ARE IN PLACE TOO} |
| 10/27/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | Nick |
| 11/15/2023 | ENGR Engineering Final | N/A | Not Ready | no van accessible ADA parking and stacked fence panels still present. reschedule for November 20, 2023. Good to grant TCO 2 |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0108
Permit Description: Site/Grading/Swppp - Popeye's Louisiana Kitchen. New restaurant.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/12/2023 | SITE - SWPPP Correction Notice | Passed | ||
| 10/12/2023 | SITE - Stormwater Follow-up | Passed | ||
| 10/12/2023 | ENGR Grading Final | Passed | ||
| 10/12/2023 | SITE - SWPPP Violation Notice | Passed | ||
| 10/12/2023 | SITE - Stormwater Setup and Controls | Passed | ||
| 10/27/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 11/07/2023 | SITE - Stormwater Final Inspection | Passed | ||
| 11/07/2023 | COT - ENGR - Signage Final | Passed | ||
| 11/07/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 11/20/2023 | ENGR Engineering Final | Passed |