Permit: DP20-0231
Permit Details
Status:
Complete
Type:
Development Package
Address:
5550 E HAMPTON ST
Address NEW:
5550 E HAMPTON ST
Apply Date:
11/11/2020
Applicant:
Bobbie Varnum
Description:
SITE - Copperstate OBGyn, building addition.
Permit Reviews
Permit Number - DP20-0231
Permit Status: Complete
Permit Description: SITE - Copperstate OBGyn, building addition.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/01/2021 | DEV PKG - RESUBMITTAL | 03/31/2021 | COMPLETED |
| 04/29/2021 | DEV PKG - OK TO SUBMIT | 05/06/2021 | COMPLETED |
| 05/05/2022 | DEV PKG - OK TO SUBMIT | 06/03/2022 | COMPLETED |
| 05/06/2021 | REVISION - - 1ST | 06/08/2021 | COMPLETED |
| 06/03/2022 | REVISION - - 2ND | 06/24/2022 | COMPLETED |
| 06/27/2022 | REVISION - - 2ND | 07/25/2022 | COMPLETED |
| 11/11/2020 | DEV PKG - OK TO SUBMIT | 11/19/2020 | COMPLETED |
| 11/18/2020 | DEV PKG | 01/25/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP20-0231
Permite Description: SITE - Copperstate OBGyn, building addition.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/26/2022 | SITE - SWPPP Correction Notice | N/A | Canceled | {Activity date: 08/26/2022; Status: Not Applicable; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Are not applicable} |
| 08/26/2022 | SITE - SWPPP Violation Notice | N/A | Canceled | {Activity date: 08/26/2022; Status: Not Applicable; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Are not applicable} |
| 11/09/2022 | ENGR Engineering Final | N/A | Complete (Recurring) | Approved |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0231
Permit Description: SITE - Copperstate OBGyn, building addition.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2022 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 02/18/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - IS APPROVED} | |
| 08/23/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 07/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Minor track out noted on Hampton} ; {Activity date: 07/19/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Track out noted on Hampton. Also barricades within the right of way} ; {Activity date: 06/22/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue} ; {Activity date: 04/22/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Track out on Hampton noted at site entrances.} ; {Activity date: 04/08/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - continue} ; {Activity date: 04/06/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Minor track out noted. Ed with Caylor} | |
| 08/23/2022 | SITE - Stormwater Final Inspection | Passed | {Activity date: 08/23/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} | |
| 08/26/2022 | ENGR Grading Final | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} | |
| 08/26/2022 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/06/2022; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - IS PARTIAL SITE HAS NO CHANGES AT THIS TIME} ; {Activity date: 04/29/2022; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VVERA1 - not ready} ; {Activity date: 04/06/2022; Status: Denied; Inspector: BBENEDON; Comment: Entered by VVERA1 - Denied. No protections in place.} ; {Activity date: 04/05/2022; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Partially approved. Ed with Caylor 237-9920} | |
| 09/29/2022 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/29/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED} ; {Activity date: 09/16/2022; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VVERA1 - Not ready} ; {Activity date: 08/26/2022; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - not ready. Complete grouted riprap, accessible parking signage. Correct slope at North East accessible parking space. Secure parking blocks. Complete landscape coverings. Clean excessive dirt from parking lot. Remove conexes and temporary toilet facilities. Ed with Caylor construction @ 237-9920} | |
| 09/29/2022 | COT - ENGR - Signage Final | Passed | {Activity date: 09/29/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - APPROVED} ; {Activity date: 09/16/2022; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VVERA1 - Not ready} ; {Activity date: 08/26/2022; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - not ready. Complete grouted riprap, accessible parking signage. Correct slope at North East accessible parking space. Secure parking blocks. Complete landscape coverings. Clean excessive dirt from parking lot. Remove conexes and temporary toilet facilities. Ed with Caylor construction @ 237-9920} | |
| 11/14/2022 | ENGR Engineering Final | Passed | N/A |