*Revision #2 started 1/18/24* SITE/GRADING - Cornerstone Homes on Bellevue, multi-family, 26 units.

Permit Reviews

Permit Number - DP20-0153
Permit Status: Issued
Permit Description: *Revision #2 started 1/18/24* SITE/GRADING - Cornerstone Homes on Bellevue, multi-family, 26 units.
Start Date Submittal Complete Date Status  
03/03/2021 DEV PKG - RESUBMITTAL 03/09/2021 COMPLETED Review Details
07/01/2020 DEV PKG - OK TO SUBMIT 08/03/2020 COMPLETED Review Details
08/03/2020 DEV PKG 09/10/2020 COMPLETED Review Details
09/20/2021 DEV PKG - OK TO SUBMIT 10/11/2021 COMPLETED Review Details
10/11/2021 REVISION - - 1ST 10/25/2021 COMPLETED Review Details
11/18/2020 DEV PKG - RESUBMITTAL 01/14/2021 COMPLETED Review Details
12/23/2021 REVISION - - 1ST 02/10/2022 COMPLETED Review Details
01/18/2024 DEVELOPMENT PACKAGE NEW v.1 02/29/2024 REQUIRES RESUBMIT Review Details
05/08/2024 DEVELOPMENT PACKAGE NEW v.2 05/21/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP20-0153
Permite Description: *Revision #2 started 1/18/24* SITE/GRADING - Cornerstone Homes on Bellevue, multi-family, 26 units.
Total Outstanding Inspections - 11
Last Inspection Date Description Inspector Results Comments
06/14/2021 RSBU - Building Final N/A Canceled {Activity date: 06/14/2021; Status: Not Applicable; Inspector: DROBERTS; Comment: Entered by VLEON1 - NOT APPLICABLE IF IT IS ON THIS DEVELOPMENT PACKAGE. TALKED TO THE CONTRACTOR AND ADVISED HIM THAT THIS PERMIT DOES NOT HAVE ANY BUILDING PERMITS ASSOCIATED, AND IT IS ALSO NOT TIED TO DEMO PERMIT IF ONE WAS ISSUED FOR TIS ADDRESS. I HAVE ADVISED THEM TO SCHEDULE THEIR INSPECTION FOR THEIR ENGINEERING PRE$CONSTRUCTION MEETING 09150 WHEN THEY WOULD BE STARTING THE SITE WORK FOR THIS PROJECT.} ; {Activity date: 06/09/2021; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by BSTEVENS - DEMO OF EXISTING BUILDING IS COMPLETE} ; {Activity date: 06/09/2021; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 06/09/2021; Status: Not Applicable; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - }
06/22/2022 SITE - Stormwater Setup and Controls N/A Complete (Recurring) {Activity date: 06/22/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No activity on site at this time. Temporary fencing has been repaired and waddle has been installed.

}
08/31/2022 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 08/31/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No activity on site at this time.

} ; {Activity date: 07/15/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 06/28/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No activity on site at this time} ; {Activity date: 06/22/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No activity on site at this time. Temporary fencing has been repaired and waddle has been installed.

} ; {Activity date: 05/26/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 05/20/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 05/10/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued}
10/27/2022 PDSD Site/Engineering Division - Landscaping N/A Not Ready
10/26/2022 PDSD Site/Engineering Division - NPPO N/A Not Ready
10/27/2022 ENGR Engineering Final N/A Not Ready
10/26/2022 SITE - Stormwater Final Inspection N/A Not Ready
10/27/2022 COT - ENGR - Signage Final N/A Not Ready
04/26/2024 ENGR - Drainage Structures N/A Not Ready Unscheduled courtesy inspection.
photo documentation provided
Mike and Russ with Cornerstone homes
12/05/2023 ENGR Grading Final N/A Not Ready site is heavily impacted by cementatios waste and solid waste. no further inspections until site cleaned up.
07/08/2024 Consultation SITE N/A Partial Pass Items left to complete,
1) Seed basin, either hydro seed or hand spread, if decided to hand spread we must be present while it is being applied.
2) Pull all nursery stakes from trees
3) Remove temp power pole
4) Remove temp fence from site
5) Complete DG ground cover in ares talked about on site visit.

Security Camera system can stay until it's needed to pull out

Completed Inspections

Permit Status: Issued
Permit Number: DP20-0153
Permit Description: *Revision #2 started 1/18/24* SITE/GRADING - Cornerstone Homes on Bellevue, multi-family, 26 units.
Total Completed Inspections - 4
Date Description Inspector Results Comments
06/10/2024 PDSD Engineering Division Pre-Construction SITE Passed
07/08/2024 ENGR Paving Passed
07/08/2024 Passed
07/08/2024 Passed

Scheduled Inspections

Scheduled Inspections - DP20-0153
Status: Issued
Description: *Revision #2 started 1/18/24* SITE/GRADING - Cornerstone Homes on Bellevue, multi-family, 26 units.
Scheduled Date Description Entered By Entered Date
02/09/2023 ENGR Grading Final Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .