Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP20-0153
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Scheduled | ||
| 07/07/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Site has been rough graded. Debris piles remain. Temporary fencing in place |
| 05/19/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued |
| 05/11/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - continued. No activity on site at this time. Lot has been graded. Debris pile remains. Temporary fencing and waddle in place. |
| 04/26/2024 | ENGR Grading Final | Partial Pass | Russ with Cornerstone Please clean dirt from public Street. All concrete. |
|
| 05/07/2024 | ENGR Grading Final | Partial Pass | I went to the site and met with the Contractor to look over the trash enclosure that has been constructed at this time. All walls are ready for grout and have been approved for grout during this inspection. I advised the contractor to contact Andy Vera with Environmental Services and ask him to make a determination on the gate width that may be less than 12 feet and determine if that was going to be an issue. I’ve also asked contractor to advise Andy to send me an email in regard to this Question and what his determination will be. | |
| 12/05/2023 | ENGR Grading Final | Not Ready | site is heavily impacted by cementatios waste and solid waste. no further inspections until site cleaned up. | |
| 12/06/2023 | ENGR Grading Final | Passed | discussed need for cleanup and reinspection 12/7. | |
| 12/29/2023 | ENGR Grading Final | Partial Pass | Utility work in progress |