Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
In Revision
Type:
Development Package
Apply Date:
06/01/2020
Applicant:
William Meyer, Jr
Description:
Revision #4 Site/Grading/SWPPP - Fairview Greenhouse. MMJ cultivation facility.

Permit Reviews

Permit Number - DP20-0115
Permit Status: In revision
Permit Description: Revision #4 Site/Grading/SWPPP - Fairview Greenhouse. MMJ cultivation facility.
Start Date Submittal Complete Date Status  
01/13/2021 REVISION - - 2ND 02/04/2021 COMPLETED Review Details
05/01/2020 DEV PKG - OK TO SUBMIT 06/02/2020 COMPLETED Review Details
06/02/2020 DEV PKG 06/30/2020 COMPLETED Review Details
07/23/2021 DEV PKG - OK TO SUBMIT 08/09/2021 COMPLETED Review Details
07/31/2020 DEV PKG - RESUBMITTAL 09/02/2020 COMPLETED Review Details
08/09/2021 REVISION - - 3RD 09/23/2021 COMPLETED Review Details
09/11/2020 DEV PKG - RESUBMITTAL 09/17/2020 COMPLETED Review Details
10/15/2020 DEV PKG - OK TO SUBMIT 11/04/2020 COMPLETED Review Details
11/03/2020 DEV PKG - OK TO SUBMIT 01/13/2021 COMPLETED Review Details
11/04/2020 REVISION - - 1ST 12/03/2020 COMPLETED Review Details
11/13/2024 DEVELOPMENT PACKAGE NEW REVISION v.3 N/A IN REVIEW Review Details
09/10/2024 DEVELOPMENT PACKAGE NEW REVISION v.2 10/11/2024 REQUIRES RESUBMIT Review Details
08/23/2024 DEVELOPMENT PACKAGE NEW REVISION v.1 08/30/2024 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: In Revision
Permit Number: DP20-0115
Permite Description: Revision #4 Site/Grading/SWPPP - Fairview Greenhouse. MMJ cultivation facility.
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
12/14/2021 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 12/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No issues after storm event. Material piles and construction debris remaining in various locations on site.

} ; {Activity date: 08/30/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME WITH THE SITE. MINOR PROBLEMS WITH A DRAINAGE SWALE THAT RUNS ALONG THE SOUTHSIDE OF THE PROJECT, THIS NEEDS TO BE CLEANED ASAP SINCE IT IS BACKING UP OUT ONTO FAIRVIEW.} ; {Activity date: 04/30/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE NO ISSUES} ; {Activity date: 03/12/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Underground utility work in progress. All track out and material piles and debris are contained within the site

} ; {Activity date: 02/23/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE} ; {Activity date: 02/04/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE} ; {Activity date: 01/20/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues} ; {Activity date: 12/10/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues after a rain event} ; {Activity date: 12/10/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues after a rain event} ; {Activity date: 12/04/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No concerns, the site is behind existing location off of a private roadway.Material storage in fenced area of parking lot} ; {Activity date: 12/02/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at this time. Protections in place}
10/26/2022 SITE - Stormwater Final Inspection N/A Not Ready
10/27/2022 COT - ENGR - Signage Final N/A Not Ready
10/27/2022 ENGR Grading Final N/A Not Ready
10/27/2022 PDSD Site/Engineering Division - Landscaping N/A Not Ready
10/27/2022 ENGR Engineering Final N/A Not Ready

Completed Inspections

Permit Status: In Revision
Permit Number: DP20-0115
Permit Description: Revision #4 Site/Grading/SWPPP - Fairview Greenhouse. MMJ cultivation facility.
Total Completed Inspections - 3
Date Description Inspector Results Comments
04/30/2021 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 04/30/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 12/02/2020; Status: Partial Approval; Inspector: BBENDON; Comment: Entered by PAHUMAD1 - Partially approved. Unscheduled courtesy inspection for John with Barker at 909-6352. Provide documentation for all below ground stormwater piping. Schedule for intermediate grading inspections 09185. Alex Hines plan reviewer. Large grow facility behind PSE.} ; {Activity date: 09/30/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. No contact information provided. Interior demo in progress. Two trash containers on site. No activity on site at this time.}
11/17/2021 PDSD Site/Engineering Division - NPPO Passed {Activity date: 11/17/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 02/23/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VLEON1 - PARTIAL APPROVAL, TWO SAGUARO CACTUS HAVE BEEN MOVED AND PLACED ON PALLETS}
11/17/2021 SITE - Stormwater Setup and Controls Passed {Activity date: 11/17/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved} ; {Activity date: 12/01/2020; Status: Partial Approval; Inspector: BENEDON; Comment: Entered by PAHUMAD1 - Partially approved. John with Barker will send pictures of all stormwater controls, and signage. Email number provided.}

Documents

File Name Document Type  
REV-3_LETTER OF REVISION #3 DP20-0115.PDF DOCUMENTS VIEW
1-41 OF 34.PDF DEVELOPMENT PACKAGE VIEW
GEOTECHNICAL STUDY.PDF DOCUMENTS VIEW
REVISION LETTER, 11.25.20.PDF DOCUMENTS VIEW
REVISION LETTER, 10.14.20.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
GEOTECH.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 09.11.20.PDF DOCUMENTS VIEW
RESPONSE TO COMMENTS, 07.31.20.PDF DOCUMENTS VIEW
RESPONSE LOT COMBO LETTER, PIMACO ASSESSOR.PDF DOCUMENTS VIEW
GEOTECH MEMO1.PDF DOCUMENTS VIEW
PIMACO ADDRESSING REVIEW, PLAN, 06.30.20.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GEOTECH REPORT.PDF DOCUMENTS VIEW
MMJ AUTH LETTER, CITY OF TUCSON, 04.17.2020.PDF DOCUMENTS VIEW