Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 04/30/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by VLEON1 - |
| 12/02/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved. Unscheduled courtesy inspection for John with Barker at 909-6352. Provide documentation for all below ground stormwater piping. Schedule for intermediate grading inspections 09185. Alex Hines plan reviewer. Large grow facility behind PSE. |
| 09/30/2020 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. No contact information provided. Interior demo in progress. Two trash containers on site. No activity on site at this time. |