Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Address:
702 S 6TH AV
Apply Date:
12/26/2019
Applicant:
Description:
SITE/GRADING - Primavera 17th Street.

Permit Reviews

Permit Number - DP19-0315
Permit Status: Issued
Permit Description: SITE/GRADING - Primavera 17th Street.
Start Date Submittal Complete Date Status  
03/25/2020 DEV PKG - RESUBMITTAL 04/28/2020 COMPLETED Review Details
05/22/2020 DEV PKG - RESUBMITTAL 06/17/2020 COMPLETED Review Details
06/29/2020 DEV PKG - RESUBMITTAL 07/23/2020 COMPLETED Review Details
11/26/2019 DEV PKG - OK TO SUBMIT 12/30/2019 COMPLETED Review Details
12/30/2019 DEV PKG 02/04/2020 COMPLETED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP19-0315
Permite Description: SITE/GRADING - Primavera 17th Street.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: DP19-0315
Permit Description: SITE/GRADING - Primavera 17th Street.
Total Completed Inspections - 8
Date Description Inspector Results Comments
09/24/2020 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 09/24/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved. Shaun with LLoyd. Schedule structural inspection For perimeter fencing and retaining wall as shown on building plans. Schedule your engineering inspections for site grading and stormwater piping

} ; {Activity date: 09/01/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved. Shaun with Lloyd at 471-1530. Cypress engineering.
Post site address, install track out protection. It right of way permit is required to close sidewalk.Less than 1 acre. Primavera 17th St. project}
08/31/2021 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV}
08/31/2021 PDSD Site/Engineering Division - NPPO Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN}
08/31/2021 ENGR Engineering Final Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV}
08/31/2021 SITE - Stormwater Follow-up Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 06/16/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CONTINUE FOR 702 S 6TH AV} ; {Activity date: 03/12/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - CONTINUED FOR 710 S STONE AV AT THIS TIME, THERE ARE NO CONCERNS NOTED DURING THIS INSPECTION.} ; {Activity date: 03/12/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - CONTINUED FOR 703 N STONE AV AT THIS TIME, THERE ARE NO CONCERNS NOTED DURING THIS INSPECTION.} ; {Activity date: 03/12/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VLEON1 - CONTINUED FOR 702 S 6TH AVE - AT THIS TIME, THERE ARE NO CONCERNS NOTED DURING THIS INSPECTION.} ; {Activity date: 09/24/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time.

} ; {Activity date: 09/08/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time} ; {Activity date: 09/08/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time} ; {Activity date: 09/08/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Waddle has been installed and Rock is on site. Contractor is cutting driveway at this time.

} ; {Activity date: 09/01/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. No issues at this time

}
08/31/2021 SITE - Stormwater Final Inspection Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN}
08/31/2021 SITE - Stormwater Setup and Controls Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 09/08/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved. Track out protection has been installed.} ; {Activity date: 09/08/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved. Track out protection has been installed.
} ; {Activity date: 09/08/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Waddle has been installed and Rock is on site. Contractor is cutting driveway at this time.

} ; {Activity date: 09/01/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Partially approved. Waddle has been installed around the site perimeter perimeter}
08/31/2021 COT - ENGR - Signage Final Passed {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
710 S STONE AV} ; {Activity date: 08/31/2021; Status: Approved; Inspector: MHERENANDEZ; Comment: Entered by NGARCIA3 - APPROVED
703 S 6TH AV} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN} ; {Activity date: 08/05/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN}

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER OF RECORD.PDF DOCUMENTS VIEW
1-10 OF 10.PDF DEVELOPMENT PACKAGE VIEW
COMMENT_RESPONSE, 06.29.20.PDF DOCUMENTS VIEW
TSMR_APPROVAL_NOTICE, DS20-05.PDF DOCUMENTS VIEW
LANDSCAPE_REPOONSE.PDF DOCUMENTS VIEW
CIVIL_RESPONSE, 05.22.2020.PDF DOCUMENTS VIEW
CIVIL_RESPONSE, 03.25.2020.PDF DOCUMENTS VIEW
LANDSCAPE_RESPONSE.PDF DOCUMENTS VIEW
EMAIL_COT_MS&R.PDF DOCUMENTS VIEW
CIVIL_RESPONSE, 03.25.2020.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
DRAINAGE_STATEMENT.PDF DOCUMENTS VIEW
NPP_EXCEPTION.PDF DOCUMENTS VIEW
PIMACO ADDRESSING REVIEW, 01.06.2020.PDF DOCUMENTS VIEW