Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: DP19-0315

Parcel: Unknown


Addresses:

702 S 6TH AV

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
04/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 703 S STONE AV / REBAR FOR FOOTER NEED THREE MORE BARS AT THE END OF EACH RUN OF THE FOOTER .CONTRACTOR WILL SEND PHOTO OF THE BAR WHEN INSTALLED TODAY
08/31/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 710 S STONE AV
08/31/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 703 S 6TH AV
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
05/07/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL FOR 710 S STONE AV, TODAYS INSPECTION LOOKED AT THE SITE WALLS AT THE NORTH WEST CORNER OF THE SITE FOR GROUT PLACEMENT APPROVAL. I HAVE APPROVED THE FIRST 4 FEET OF WALL FOR THE PLACEMENT OF THE GROUT, I ALSO ADVISED JIM BURGE OF THIS APPROVAL.
05/07/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL FOR 702 S 6TH AV , TODAYS INSPECTION LOOKED AT THE SITE WALLS AT THE NORTH WEST CORNER OF THE SITE FOR GROUT PLACEMENT APPROVAL. I HAVE APPROVED THE FIRST 4 FEET OF WALL FOR THE PLACEMENT OF THE GROUT, I ALSO ADVISED JIM BURGE OF THIS APPROVAL.
05/07/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL FOR 703 S STONE AV, TODAYS INSPECTION LOOKED AT THE SITE WALLS AT THE NORTH WEST CORNER OF THE SITE FOR GROUT PLACEMENT APPROVAL. I HAVE APPROVED THE FIRST 4 FEET OF WALL FOR THE PLACEMENT OF THE GROUT, I ALSO ADVISED JIM BURGE OF THIS APPROVAL.
04/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 710 S STONE AV/ REBAR FOR FOOTER NEED THREE MORE BARS AT THE END OF EACH RUN OF THE FOOTER .CONTRACTOR WILL SEND PHOTO OF THE BAR WHEN INSTALLED TODAY
04/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 702 S 6TH AV / REBAR FOR FOOTER NEED THREE MORE BARS AT THE END OF EACH RUN OF THE FOOTER .CONTRACTOR WILL SEND PHOTO OF THE BAR WHEN INSTALLED TODAY .
03/22/2021 ENGR Grading Final MHERNANDEZ Partial Approval Entered by VLEON1 - PARTIAL FOR 703 S STONE AV - NEED TO GROUT THE TWO FRONT CORNERS
03/22/2021 ENGR Grading Final MHERNANDEZ Partial Approval Entered by VLEON1 - PARTIAL FOR 710 S STONE AV - NEED TO GROUT THE TWO FRONT CORNERS
03/22/2021 ENGR Grading Final MHERNANDEZ Partial Approval Entered by VLEON1 - PARTIAL 702 S 6TH AV NEED TO GROUT THE TWO FRONT CORNERS
03/18/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 702 S 6TH AV - STILL NEEDS STEEL IN THE CORNERS .RESCHEDULE FOR MONDAY
03/18/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 710 S STONE AVE - STILL NEEDS STEEL IN THE CORNERS .RESCHEDULE FOR MONDAY
03/18/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 703 N STONE AVE - STILL NEEDS STEEL IN THE CORNERS .RESCHEDULE FOR MONDAY
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 710 S STONE AV AT THIS TIME, OK TO POUR THE TRASH ENCLOSURE FOOTERS AT THIS TIME.
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 703 N STONE AV AT THIS TIME, OK TO POUR THE TRASH ENCLOSURE FOOTERS AT THIS TIME.
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 702 S 6TH AV AT THIS TIME, OK TO POUR THE TRASH ENCLOSURE FOOTERS AT THIS TIME.
09/24/2020 ENGR Grading Final BBENEDON Not ready for Inspection Entered by JSCHNEI2 - Not ready. Shaun with LLoyd. Needs building inspection of footings.
08/31/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 710 S STONE AV
08/31/2021 ENGR Grading Final MHERENANDEZ Approved Entered by NGARCIA3 - APPROVED 703 S 6TH AV
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
08/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN
06/16/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 702 S 6TH AV - GRADING FOR SIDEWALK
06/10/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 710 S STONE AV/FORMING FOR CURB AND SIDEWALK HEADER CURB FOR GATED FENCE.
06/10/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 703 N STONE AV/FORMING FOR CURB AND SIDEWALK HEADER CURB FOR GATED FENCE.
06/10/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 702 S 6TH AV/FORMING FOR CURB AND SIDEWALK HEADER CURB FOR GATED FENCE.
06/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE FOR 710 S STONE AVE - FORMING FOR STEM WALLS
05/07/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - FOR 703 S STONE AV CREWS WORKING ON THE TRASH ENCLOSURE, THEY WILL BE POURING THE FLOOR EITHER THIS WEEKEND OR NEXT MONDAY.
05/07/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - FOR 710 S STONE AV CREWS WORKING ON THE TRASH ENCLOSURE, THEY WILL BE POURING THE FLOOR EITHER THIS WEEKEND OR NEXT MONDAY.
05/07/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - FOR 702 S 6TH AV - CREWS WORKING ON THE TRASH ENCLOSURE, THEY WILL BE POURING THE FLOOR EITHER THIS WEEKEND OR NEXT MONDAY.
04/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 710 S STONE AV - WENT OVER THE DETAILED DRAWINGS FOR THE SCUPPER OUT IN THE STREET AND RETAINING WALL ON THE NORTH END OF BUILDING .AND TRUNCATED DOMES.
04/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN 703 S STONE AV - WENT OVER THE DETAILED DRAWINGS FOR THE SCUPPER OUT IN THE STREET AND RETAINING WALL ON THE NORTH END OF BUILDING .AND TRUNCATED DOMES.
04/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FOR 702 S 6TH AVE - WENT OVER THE DETAILED DRAWINGS FOR THE SCUPPER OUT IN THE STREET AND RETAINING WALL ON THE NORTH END OF BUILDING .AND TRUNCATED DOMES.
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 710 S STONE AV AT THIS TIME. WORK MAINLY ON THIS SITE IS VERTICAL. SITE WORK WILL CONTINUE WITHIN THE NEXT 2 WEEKS, THE CONTRACTOR WILL SCHEDULE THIS INSPECTION AT THAT TIME.
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 703 N STONE AV AT THIS TIME. WORK MAINLY ON THIS SITE IS VERTICAL. SITE WORK WILL CONTINUE WITHIN THE NEXT 2 WEEKS, THE CONTRACTOR WILL SCHEDULE THIS INSPECTION AT THAT TIME.
03/12/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED FOR 702 S 6TH AV AT THIS TIME. WORK MAINLY ON THIS SITE IS VERTICAL. SITE WORK WILL CONTINUE WITHIN THE NEXT 2 WEEKS, THE CONTRACTOR WILL SCHEDULE THIS INSPECTION AT THAT TIME.
09/24/2020 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Contractor installing perimeter fencing.