Permit: DP19-0288
Permit Details
Apply Date:
11/20/2019
Applicant:
Description:
SITE/GRADING/SWPPP - Newport at Amphi, new multi-family residential.
Permit Reviews
Permit Number - DP19-0288
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - Newport at Amphi, new multi-family residential.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2020 | DEV PKG - RESUBMITTAL | 03/09/2020 | COMPLETED |
| 03/12/2020 | DEV PKG - RESUBMITTAL | 03/12/2020 | COMPLETED |
| 10/22/2019 | DEV PKG - OK TO SUBMIT | 11/27/2019 | COMPLETED |
| 11/27/2019 | DEV PKG | 01/02/2020 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0288
Permit Description: SITE/GRADING/SWPPP - Newport at Amphi, new multi-family residential.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/05/2021 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/05/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09150, 09152. Approved} ; {Activity date: 08/17/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Partially approved. Track out protection added to South entrance.} ; {Activity date: 07/13/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09154, 09152. Continued. Notable track out on Stone Avenue, protections recommended. Don with Tofel } ; {Activity date: 11/25/2020; Status: Partial Approval; Inspector: BBENENDON; Comment: Entered by PAHUMAD1 - Partially approved. Controls have been installed on the south and east portions of the site perimeter. Track out protection has been installed at both entrances. Provide concrete containment. } ; {Activity date: 11/03/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. No track out protection in place } ; {Activity date: 10/30/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. No track out Protection in place} ; {Activity date: 10/16/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Not ready} |
|
| 11/05/2021 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/05/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09150, 09152. Approved} ; {Activity date: 11/25/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. Engineering does not look at the structural components of the perimeter fencing, as stated in the preconstruction meeting October 16. Don with Tofel/ Dent Detail 601 provided.} ; {Activity date: 10/16/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved} ; {Activity date: 10/16/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved } ; {Activity date: 10/16/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Partially approved. Don with Tofel/ Dent construction at989-1618. Northwest corner of Prince and stone. New multi family housing complex. Post to address. No work has started at this time. Demolition of previous structure to start in two weeks. Temporary fencing, addressing, SWPPP scheduled for installation. Do not block pedestrian walkway with temporary fencing. Install stormwater controls as needed. Track out protection, concrete containment. Schedule 09152 inspection. Schedule 0915 for inspections biweekly to start. Engineering does not look at the structural components of the perimeter fencing, however I do need to ensure that the openings are installed as shown. Any changes to grading and drainage from the approved drawings would require approved revisions. Trash enclosure requires inspection and compliance with COT standard detail 6.01 Below ground storm water piping and water harvesting and dry well require inspection. Use code 09185. Pay attention to all water harvesting and landscaping details shown. Call for inspection prior to landscaping.} |
|
| 12/17/2021 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 12/17/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} | |
| 12/17/2021 | SITE - Stormwater Follow-up | Passed | {Activity date: 12/17/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 12/02/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. The dirt in the streets have been removed and the temporary fencing has been reinstalled along Stone Avenue} ; {Activity date: 12/01/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Dirt placed in the street at temporary yard access for landscaping purposes.} ; {Activity date: 11/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. All barricades within the roadway have been removed. The street has been swept. Pavement is complete. Landscaping operations in progress } ; {Activity date: 11/18/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time. Landscaping work in progress 3601 N Stone Ave, } ; {Activity date: 11/05/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues or concerns at this time. Landscaping only in progress progress} ; {Activity date: 10/08/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Minor track out noted on Stone Avenue.} ; {Activity date: 10/05/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Track out on Stone Avenue.} ; {Activity date: 10/01/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - . Continued. Notable amount of muddy track out on Stone Avenue.} ; {Activity date: 10/01/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Notable amount of muddy track out on Stone Avenue.} ; {Activity date: 09/30/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continue. Muddy track out on Stone Avenue, pedestrian barricades have been removed. South entrance and west parking area paved. } ; {Activity date: 09/03/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Track out noted after last rain event. Protection rock in place} ; {Activity date: 08/26/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. And no issues at this time. Stormwater protections are in place. } ; {Activity date: 08/20/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Notable track out on Prince Avenue. Controls in place.} ; {Activity date: 08/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continue. Barricades along east side entrance, right of way work in progress. Minor track out noted at South entrance. } ; {Activity date: 08/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Check out has been removed. Driveway work in right away has started. } ; {Activity date: 08/05/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 3601 Continued. Track out on Stone. Contractor still using East entrance} ; {Activity date: 07/23/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued. Muddy track out on Stone Avenue after rain event. There’s no track out protection in place} ; {Activity date: 07/20/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Notable track out on Stoner Avenue} ; {Activity date: 07/15/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - continued. trackout present} ; {Activity date: 07/13/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09154, 09152. Continued. Notable track out on Stone Avenue, protections recommended. Don with Tofel } ; {Activity date: 07/08/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Notable amount of track out and stone remains.} ; {Activity date: 06/16/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued FOR 3601 N STONE AV. No track out. Protections remain in place} ; {Activity date: 05/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued FOR 3601 N STONE AV. No issues or concerns at this time. South entrance only used. Minor track of protections in place } ; {Activity date: 05/05/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continue FOR 3601 N STONE AV. No issues or concerns at this time. Roy with Canyon builders is keeping all veterans is clean.} ; {Activity date: 04/15/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE FOR 3601 N STONE AVE - No issues or concerns at this time.} ; {Activity date: 03/24/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Minor truck out noted at south entrance after rain event.} ; {Activity date: 03/02/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues at this time. Both entrances are being used.} ; {Activity date: 02/12/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE FOR 3601 N STONE AVE, VERY MINOR TRACK OUT, CONTROLS IN PLACE} ; {Activity date: 01/28/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - Continued FOR 3601 N STONE AVE. Muddy track out noted on Prince Road. Don with TOEFL dent will take correct of action.} ; {Activity date: 01/22/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUE FOR 3601 N STONE AVE NO ISSUES AT THIS TIME SOUTH SITE ENTRANCE IS IN USE} ; {Activity date: 12/22/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Contractors utilizing south entrance onto Prince Road. The gate for the Stone Avenue entrance is closed.} ; {Activity date: 12/15/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by VLEON1 - CONTINUED, MINOR TRACK OUT NOTED ON PRINCE RD.} ; {Activity date: 12/15/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Minor track out noted on Prince Road} ; {Activity date: 12/09/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at either site entrance} ; {Activity date: 11/25/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. No issues at this time} ; {Activity date: 11/19/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - continued no issues} ; {Activity date: 11/02/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Minor trackout noted on Stone Avenue.} ; {Activity date: 10/16/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Continued. Demolition to start within the next two weeks. Don with Tofel/ Dent Construction will schedule inspections in coordination with SWPPP. On a biweekly basis.} |
|
| 12/23/2021 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3631 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3601 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 20 W PRINCE RD} ; {Activity date: 12/16/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VVERA1 - Partially approved} ; {Activity date: 12/15/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - . Not ready} ; {Activity date: 12/14/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VVERA1 - Not ready } ; {Activity date: 12/10/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready at this time} ; {Activity date: 11/30/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VVERA1 - Partially approved. continue removing construction debris prior to installing specified materials. Plant, irrigation and ground covering installation of progress} ; {Activity date: 11/24/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - . Continued. Remove debris piles prior to installing stabilization materials. Stake trees as required. 3601 N Stone Ave } ; {Activity date: 11/17/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VVERA1 - Partially approved. Provide tree staking as shown in plan details} |
|
| 12/23/2021 | ENGR Engineering Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3631 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3601 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 20 W PRINCE RD} ; {Activity date: 12/16/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VVERA1 - Not ready. Dirt must be removed from the street next to the curb prior to final approval.} |
|
| 12/23/2021 | ENGR Grading Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. 9190 20 W PRINCE RD} ; {Activity date: 10/30/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Continued. Demolition in progress.} |
|
| 12/23/2021 | SITE - Stormwater Final Inspection | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3631 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3601 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 20 W PRINCE RD } ; {Activity date: 12/17/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Not ready. Provide not} ; {Activity date: 12/17/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Provide not} |
|
| 12/23/2021 | COT - ENGR - Signage Final | Passed | {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3631 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 3601 N STONE AV} ; {Activity date: 12/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Approved. Please approve all inspections for development package permit and change status to final approval. 20 W PRINCE RD} |