| 12/10/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by VVERA1 - Approved |
| 09/16/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Bollards |
| 09/15/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Install trash enclosure slab as shown in detail 601 |
| 09/14/2021 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. |
| 09/14/2021 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by VVERA1 - Not ready.
|
| 12/22/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Pre-grout to 6 feet. |
| 12/21/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Pre-grout |
| 12/18/2020 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready. |
| 12/18/2020 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by RSALDAT1 - Not ready, working on it Don w Tofel |
| 12/02/2020 |
ENGR Grading Final |
BBENDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved. |
| 12/02/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved. Trash enclosure footing. Check for Ballard location. Reschedule rebar inspection for pre-slab and pre-grout
|
| 12/02/2020 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by PAHUMAD1 - Not ready. Don with TOEFL dent |
| 11/25/2020 |
ENGR Grading Final |
BBENENDON |
Not ready for Inspection |
Entered by PAHUMAD1 - |
| 11/25/2020 |
ENGR Grading Final |
BBENEDON |
Not ready for Inspection |
Entered by PAHUMAD1 - Not ready. Engineering does not look at the structural components of the perimeter fencing, as stated in the preconstruction meeting October 16. Don with Tofel/ Dent
Detail 601 provided. |
| 12/10/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by VVERA1 - Approved |
| 11/09/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Parking shade canopy installations in progress.
3601 N Stone Ave |
| 11/02/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Footings for parking canopy have been marked. Landscaping in progress.
3601 N Stone Ave |
| 10/26/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VVERA1 - Continued. Final grading
|
| 10/20/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VVERA1 - Partially approved. Accessible spaces and striping |
| 10/19/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by NGARCIA3 - . Partially approved. Pavement installed
3601 N Stone Ave |
| 09/28/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VVERA1 - 09185. Continued. Final grading in progress. Work within the right of way.
|
| 09/24/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VVERA1 - 09185. Partially approved. Grading, curbs |
| 09/14/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - . Partially approved. Truncated dome’s not required for loading zone access. Install as shown per plan. Don with Tofel.
|
| 09/14/2021 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by VVERA1 - Partially approved. Truncated dome’s not required for loading zone access. Install as shown per plan. Don with Tofel. |
| 08/25/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Site grading |
| 07/27/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Architectural plan for the dumpster gate is acceptable to engineering. |
| 07/08/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Work within the right of way on prince. |
| 06/18/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued FOR 20 W PRINCE RD. Contractor working within right of way. Lane closure barricades in place
|
| 05/25/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE FOR 3601 N STONE AV - No grading activate this time. Contractor focusing on building exterior construction. |
| 05/11/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued FOR 3601 N STONE AV. Don with TOEFL dent. Starting site work beginning with demolition of existing entrance and construction of new site entrance. Don will get right of way inspections for work outside of the property line. |
| 05/05/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - Continued FOR 3601 N STONE AV. Building construction progress. No grading activity at this time. |
| 02/12/2021 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VLEON1 - CONTINUE FOR 3601 N STONE AV BUILDING CONSTRUCTION IN PROGRESS NO SITE WORK AT THIS TIME |
| 12/22/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Trash enclosure |
| 12/15/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued |
| 12/09/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by PAHUMAD1 - Continued. Contractors installing soil piping |
| 12/02/2020 |
ENGR Grading Final |
BBENDON |
Partial Approval |
Entered by PAHUMAD1 - Partially approved. Trash enclosure footings and rough grading.
|
| 11/19/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Over excavation and grading in progress |
| 11/04/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Completion of demolition |
| 12/17/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by NGARCIA3 - Approved |
| 12/23/2021 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by NGARCIA3 - Approved. 9190
20 W PRINCE RD |
| 10/30/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by PAHUMAD1 - Continued. Demolition in progress. |