Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
01/22/2019
Applicant:
Ryan Stucki
Description:
GRADING/SWPPP - TEXAS INSTRUMENTS TUCSON

Permit Reviews

Permit Number - DP19-0015
Permit Status: Complete
Permit Description: GRADING/SWPPP - TEXAS INSTRUMENTS TUCSON
Start Date Submittal Complete Date Status  
01/24/2019 DEV PKG 01/29/2019 COMPLETED Review Details
01/29/2019 DEV PKG - RESUBMITTAL 02/05/2019 COMPLETED Review Details
02/05/2019 DEV PKG - RESUBMITTAL 02/05/2019 COMPLETED Review Details
12/19/2018 DEV PKG - OK TO SUBMIT (GRADING ONLY) 01/23/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP19-0015
Permit Description: GRADING/SWPPP - TEXAS INSTRUMENTS TUCSON
Total Completed Inspections - 9
Date Description Inspector Results Comments
04/01/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 04/01/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
04/15/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 04/15/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by CBELL1 - } ; {Activity date: 03/25/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - engineer in preconstruction meeting. Walks site with grading contractor and GC went over controls that need to be added
}
10/26/2020 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/26/2020; Status: Approved; Inspector: Rledonne; Comment: Entered by RLEDONN1 - }
10/26/2020 COT - ENGR - Signage Final Passed {Activity date: 10/26/2020; Status: Approved; Inspector: Rledonne; Comment: Entered by RLEDONN1 - }
04/06/2022 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/26/2020; Status: Partial Approval; Inspector: RDELONNE; Comment: Entered by PAHUMAD1 - Partial approval. OK for TCO engineering only. Complete all work on on approved plans keynotes and provide all certain letters and As requested in past inspections notes.} ; {Activity date: 10/26/2020; Status: Approved; Inspector: Rledonne; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. Walk Site went over staking of trees.} ; {Activity date: 09/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. Walk Site went over staking of trees.} ; {Activity date: 08/05/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. Working on arrogation lines on west side of site.No trees or plants have been planted at this time.} ; {Activity date: 07/29/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. Talked with landscape foreman getting ready to install main irrigation line. Most that has been installed is covered.} ; {Activity date: 07/29/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. Talked with landscape foreman getting ready to install main irrigation line. Most that has been installed is covered.} ; {Activity date: 07/23/2020; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - IS NOT READY AT THIS TIME, LANDSCAPING FOR THIS SITE HAS NOT BEEN STARTED IN MOST OF THE AREAS THROUGHOUT THIS SITE.
CURRENTLY THE SITE WORK HAS BEEN STOPPED DUE TO THE RAINS TODAY. THE CONTRACTOR HAS POURED CURBS WITHIN THE SITE AND ARE CURRENTLY WORKING ON THE BUILDING OF THE BASE GRADE THAT IS BENEATH THE FUTURE PAVEMENT.
NO CONCERNS ON THE SITE AT THIS TIME, DRAINAGE APPEARS TO BE WORKING AS DESIGNED.} ; {Activity date: 06/17/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No landscaping being installed at this time.
} ; {Activity date: 06/17/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. No landscaping being installed at this time.}
04/06/2022 ENGR Engineering Final Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 10/26/2020; Status: Partial Approval; Inspector: RDELONNE; Comment: Entered by PAHUMAD1 - Partial approval. OK for TCO engineering only. Complete all work on on approved plans keynotes and provide all certain letters and As requested in past inspections notes.} ; {Activity date: 03/21/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by CBELL1 - I have asked the contractors to call in Inspection 9150 Engineering Pre-con in for next Monday. Also the contractor has been advised to call in Inspection 09154 Stormwater Followup Every two weeks till the project has all the pavement and asphalt down.}
04/06/2022 SITE - Stormwater Follow-up Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 12/02/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No concerns at this time.

} ; {Activity date: 11/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by PAHUMAD1 - Continue. No track out no concerns at this time.} ; {Activity date: 10/26/2020; Status: Approved; Inspector: Rledonne; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/23/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 09/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. Walk say with Bailey With Sunt went over corrections that need to be made.
} ; {Activity date: 09/09/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. Walk say with Bailey With Sunt went over corrections that need to be made.
} ; {Activity date: 08/25/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RSALDAT1 - Continue. Transitioning from temporary controls to permanent controls.} ; {Activity date: 07/16/2020; Status: Continued; Inspector: RLEDONNE; Comment: Entered by JSCHNEI2 - Continue. No concerns at this time.} ; {Activity date: 12/23/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Need to make repairs to waddle on south west side of site.} ; {Activity date: 12/23/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Need to make repairs to waddle on south west side of site.} ; {Activity date: 12/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Met with GC went over a couple of minor repairs to controls.} ; {Activity date: 12/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Met with GC went over a couple of minor repairs to controls.} ; {Activity date: 11/14/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 10/30/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 05/23/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with GC talked about controls on north east corner of property to be repaired. Construction fencing coming down on north side of property.
} ; {Activity date: 04/01/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - No concerns at this time.}
04/06/2022 ENGR Grading Final Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
04/06/2022 SITE - Stormwater Final Inspection Passed {Activity date: 04/06/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER.PDF DOCUMENTS VIEW
SWPPP REPORT UNDER DP18-0301.PDF DOCUMENTS VIEW
1-5 OF 5.PDF DEVELOPMENT PACKAGE VIEW