Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP18-0156
Permit Details
Apply Date:
06/22/2018
Applicant:
Jennifer Kimura
Description:
E SITE/GRADE/SWPPP- TUCSON AIRPORT DC1st Revision approved 01/16/19 - sheets C2.0, C2.2, C3.0, C3.
Permit Reviews
Permit Number - DP18-0156
Permit Status: Complete
Permit Description: E SITE/GRADE/SWPPP- TUCSON AIRPORT DC1st Revision approved 01/16/19 - sheets C2.0, C2.2, C3.0, C3.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/22/2018 | DEV PKG - OK TO SUBMIT | 06/29/2018 | COMPLETED |
06/29/2018 | DEV PKG | 08/22/2018 | COMPLETED |
08/30/2018 | DEV PKG - RESUBMITTAL | 10/05/2018 | COMPLETED |
10/05/2018 | DEV PKG - RESUBMITTAL | 11/02/2018 | COMPLETED |
12/05/2018 | DEV PKG - REVISION | 01/07/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0156
Permit Description: E SITE/GRADE/SWPPP- TUCSON AIRPORT DC1st Revision approved 01/16/19 - sheets C2.0, C2.2, C3.0, C3.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/04/2018 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 12/04/2018; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } | |
12/05/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 12/05/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/04/2018; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by CBELL1 - Left open for information, GC for Nitti builders is Johnny at 6:02 694 5650. The Job trailer is located across the street. Call for stormwater inspections} ; {Activity date: 11/21/2018; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - I spoke with Johnny the GC with Nitti builders at 6:02 694 5650. I asked him to schedule a pre-construction meeting once the plans and permits are on site.} | |
12/17/2019 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 12/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/16/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Rick is on site only until 3 PM} | |
12/17/2019 | COT - ENGR - Signage Final | Passed | {Activity date: 12/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/16/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Rick is on site only until 3 PM} | |
01/06/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/12/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Landscapers are still installed. I spoke with the superintendent Rick about keeping the grade adjacent to the sidewalk, lower than the sidewalk and double staking the trees.} ; {Activity date: 12/11/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor is only on site until 3 PM. will reschedule the inspection and I’ll try to make it there earlier to accommodate. } ; {Activity date: 12/03/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Installation in progress} ; {Activity date: 11/14/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor installing landscaping irrigation} ; {Activity date: 11/04/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Installing irrigation } |
|
01/06/2020 | ENGR Engineering Final | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/03/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } ; {Activity date: 12/18/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - ok to install ground coverings} | |
01/06/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/05/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues} ; {Activity date: 12/04/2019; Status: Continued; Inspector: MRAMBER; Comment: Entered by SFLORES2 - Controls are still in place.} ; {Activity date: 12/03/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Controls are still in place.} ; {Activity date: 11/22/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues or concerns in this time. Controls are still in place} ; {Activity date: 11/14/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues.} ; {Activity date: 11/04/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/23/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Controls are still in place.} ; {Activity date: 10/10/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Controls are still in place} ; {Activity date: 10/09/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Construction materials and debris on sidewalk} ; {Activity date: 10/02/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Streets have been swept} ; {Activity date: 09/24/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Muddy track out into driveway and streets due to recent rains.} ; {Activity date: 09/20/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by VFLORES1 - Minor track out no issues at this time} ; {Activity date: 09/10/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Streets are dusty but have been swept.} ; {Activity date: 08/26/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No tracked out from this job site on to public streets, however there is mud in private driveway west side. Of site to be cleaned.} ; {Activity date: 08/23/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Protections have been installed at drainage structures.} ; {Activity date: 08/21/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I spoke with Tricon, doing city of Tucson work in the right of way, and requested the tape protect the drainage structure from dirt contamination. The contractor said he would. Sandy will place controls at the drainage structure inlets as a precaution} ; {Activity date: 08/19/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Tricon is performing work in the street. My only concern is preventing dirt from entering drainage structure.} ; {Activity date: 08/14/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - There is track out in the private driveway to the west. Brosuis to the east is closed} ; {Activity date: 07/17/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - No issues at this time.} ; {Activity date: 07/09/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I’ll track out has been cleaned up, and garbage has been cleaned from the site.} ; {Activity date: 07/08/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Some track out rock in the street. Stacy will have his labor sweep site entrances} ; {Activity date: 07/05/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by VFLORES1 - A new entrance at the northeast corner has been installed and track out protection is in place.} ; {Activity date: 07/02/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Minor track out at the north west entrance and some rocks in the street at the southeast entrance. Stacy will take care of it.} ; {Activity date: 06/24/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Notable rocks tracked out into street.} ; {Activity date: 06/20/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Newly Installed catch basins have not been protected and have dirt in them that need to be removed. Protect all newly installed drainage systems during construction} ; {Activity date: 06/17/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - There is track out at the same entrance and the SWPPP sign has fallen down} ; {Activity date: 05/28/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no concerns at this time} ; {Activity date: 05/21/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor will make the corrections in the morning.} ; {Activity date: 05/20/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Corrections still required and south end of site.} ; {Activity date: 05/16/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I reminded Sandy to sweep up the track out rock that is in the street and to correct the waddle that has fallen into the street.} ; {Activity date: 05/14/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Minor track} ; {Activity date: 04/04/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There is some minor track out and rocks to be noted. I spoke with GC Sandy and reminded him to call for engineering inspections periodically and to keep Wattles in place as needed} ; {Activity date: 02/21/2019; Status: Continued; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - There are no issues at this time, however the requested corrections have not been made. unscheduled inspection.} ; {Activity date: 02/14/2019; Status: Denied; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - Corrections to controls on sw corner have not been made as promised.} ; {Activity date: 02/13/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - I met with the new GC Sandy. We talked about the waddle along the south and west sides of the site that need repair where they have been moved or disturbed. Note a 2 foot overlap is required for waddle placement. There are no track out issues to be noted at this time} ; {Activity date: 02/11/2019; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS ON THIS SITE AT THIS TIME.} ; {Activity date: 12/04/2018; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - No issues at this time.} |
|
01/06/2020 | ENGR Grading Final | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
01/06/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 01/06/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/04/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by SFLORES2 - Remove all controls and terminate NOI after completing groundcovering} ; {Activity date: 09/26/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS FOR THIS SITE PRIOR TO SCHEDULING THIS INSPECTION} |