Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 01/06/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 01/03/2020 |
PDSD Site/Engineering Division - Landscaping |
RLEDONNE |
Not ready for Inspection |
Entered by SFLORES2 - |
| 12/20/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by SFLORES2 - double stake all trees and complete ground coverings |
| 01/06/2020 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 12/12/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Landscapers are still installed. I spoke with the superintendent Rick about keeping the grade adjacent to the sidewalk, lower than the sidewalk and double staking the trees. |
| 12/11/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Contractor is only on site until 3 PM. will reschedule the inspection and I’ll try to make it there earlier to accommodate.
|
| 12/03/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Partial Approval |
Entered by DMERANZ1 - Installation in progress |
| 11/14/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Continued |
Entered by DMERANZ1 - Contractor installing landscaping irrigation |
| 11/04/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Installing irrigation
|