Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP18-0139
Permit Details
Apply Date:
06/08/2018
Applicant:
Description:
E SITE/GRADING/SWPPP - RISAS DENTAL AND BRACES
Permit Reviews
Permit Number - DP18-0139
Permit Status: Complete
Permit Description: E SITE/GRADING/SWPPP - RISAS DENTAL AND BRACES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/07/2018 | DEV PKG - OK TO SUBMIT | 06/13/2018 | COMPLETED |
06/14/2018 | DEV PKG | 07/18/2018 | COMPLETED |
08/03/2018 | DEV PKG - RESUBMITTAL | 08/31/2018 | COMPLETED |
10/01/2018 | DEV PKG - RESUBMITTAL | 11/05/2018 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP18-0139
Permit Description: E SITE/GRADING/SWPPP - RISAS DENTAL AND BRACES
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/12/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 03/12/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 03/11/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by CBELL1 - Track out protection is in place and a couple of long 2 x 4’s have been placed next to the driveway at the curb. The site is less than 1 acre according to the plans. } |
|
07/17/2019 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 07/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/17/2019 | SITE - Stormwater Follow-up | Passed | {Activity date: 07/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 05/10/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by VFLORES1 - Contractor has begun installing curbs, and has removed track of protection for final grading.} ; {Activity date: 05/02/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - No issues at this time, no track out present. Protections in place} ; {Activity date: 04/26/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - Minor track out onto private road noted.} ; {Activity date: 04/18/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no issues or concerns at this time} ; {Activity date: 04/03/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no concerns at this time} ; {Activity date: 03/21/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no issues at this time. Note the mud in the streets is accumulation from a low spot in the private road not from the job site} ; {Activity date: 03/11/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - there are no concerns at this time} ; {Activity date: 03/12/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - Even with the recent rains there are no issues or concerns at this time} | |
07/17/2019 | COT - ENGR - Signage Final | Passed | {Activity date: 07/17/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/24/2019 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/24/2019 | ENGR Engineering Final | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/24/2019 | ENGR Grading Final | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/24/2019 | SITE - Stormwater Final Inspection | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } | |
07/24/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 07/24/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 03/12/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - I met with Dan from BFL contractors. We discussed stormwater requirements, concrete containment, and harvesting areas to be installed, also trash enclosure requirements. I suggested that he get a copy of his development package permit. We walked the site and looked at stormwater controls and have no current concerns at this time. Note there is flooding on the private street to the south not due to site construction.} ; {Activity date: 03/11/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - This was an unscheduled inspection, I stop by the site met the superintendent with DFL his name is Dan I showed him his DP number on his plans approved by Alexander Hines and I requested that he schedule 09050 preconstruction meeting. } |