Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP18-0081
Permit Details
Apply Date:
04/05/2018
Applicant:
Description:
*Revision #5 started 3/6/24 (update grading, add a new driveway)* TENTATIVE PLAT - Houghton Town Center. Lots 34-53, and, Blocks K thru N. Lots 34 thru 67, and, Blocks K thru N.
Permit Reviews
Permit Number - DP18-0081
Permit Status: Issued
Permit Description: *Revision #5 started 3/6/24 (update grading, add a new driveway)* TENTATIVE PLAT - Houghton Town Center. Lots 34-53, and, Blocks K thru N. Lots 34 thru 67, and, Blocks K thru N.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/07/2022 | DEV PKG - OK TO SUBMIT | 03/16/2022 | COMPLETED |
04/05/2018 | DEV PKG - OK TO SUBMIT | 04/05/2018 | COMPLETED |
04/05/2018 | TENTATIVE PLAT REVIEW | 06/08/2018 | COMPLETED |
04/05/2022 | DEV PKG - OK TO SUBMIT | 06/02/2022 | COMPLETED |
06/02/2022 | REVISION - - 2ND | 06/22/2022 | COMPLETED |
06/08/2018 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 07/26/2018 | COMPLETED |
07/26/2018 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 11/04/2019 | COMPLETED |
08/17/2022 | REVISION - - 2ND | 10/05/2022 | COMPLETED |
10/04/2019 | DEV PKG - OK TO SUBMIT | 11/07/2019 | COMPLETED |
11/07/2019 | DEV PKG - REVISION | 12/16/2019 | COMPLETED |
12/18/2019 | DEV PKG - REVISION | 01/16/2020 | COMPLETED |
08/30/2023 | DEVELOPMENT PACKAGE NEW v.2 | 09/05/2023 | REQUIRES RESUBMIT |
03/06/2024 | DEVELOPMENT PACKAGE NEW v.1 | 04/02/2024 | IN REVIEW |
05/06/2024 | DEVELOPMENT PACKAGE NEW v.2 | 06/03/2024 | APPROVED |
04/03/2024 | DEVELOPMENT PACKAGE NEW v.1 | 05/01/2024 | REQUIRES RESUBMIT |
07/20/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/30/2023 | REQUIRES RESUBMIT |
09/08/2023 | DEVELOPMENT PACKAGE NEW v.3 | 11/16/2023 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP18-0081
Permite Description: *Revision #5 started 3/6/24 (update grading, add a new driveway)* TENTATIVE PLAT - Houghton Town Center. Lots 34-53, and, Blocks K thru N. Lots 34 thru 67, and, Blocks K thru N.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
06/13/2023 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | Installing 45 inch SRP pipe the first run is good backfill |
10/24/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns at this time |
06/12/2023 | ENGR Grading Final | N/A | Complete (Recurring) | Mortal land install a 48 inch storm drain pipe on the north east part of the project. |
Completed Inspections
Permit Status: Issued
Permit Number: DP18-0081
Permit Description: *Revision #5 started 3/6/24 (update grading, add a new driveway)* TENTATIVE PLAT - Houghton Town Center. Lots 34-53, and, Blocks K thru N. Lots 34 thru 67, and, Blocks K thru N.
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/10/2024 | ENGR Grading Final | Passed | ||
01/10/2024 | SITE - Stormwater Final Inspection | Passed | ||
01/17/2024 | ENGR Engineering Final | Passed | ||
01/17/2024 | COT - ENGR - Signage Final | Passed |