Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP18-0081

Parcel: 99999999A


Addresses:

9044 S HOUGHTON RD


Inspection Status: Not Ready

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP18-0081

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 SITE - Stormwater Follow-up Not Ready
01/02/2024 SITE - Stormwater Follow-up Complete (Recurring) There are no concerns at this time. Contractor is still working on completing the landscaping and grading around the site.
06/30/2023 SITE - Stormwater Follow-up Complete (Recurring) NO CONCERNS AT THIS TIME
07/11/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time. Everything looks good.
07/18/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time and everything looks pretty good
07/28/2023 SITE - Stormwater Follow-up Not Ready Complete all work is shown on the approved plans
08/08/2023 SITE - Stormwater Follow-up Complete (Recurring) contractor is still working on the basins. the wattles are still in place.
08/15/2023 SITE - Stormwater Follow-up Complete (Recurring) no concerns at this time.
08/22/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
08/29/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
09/12/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time. Ran this morning. Everything’s fridge really good here.
09/19/2023 SITE - Stormwater Follow-up Complete (Recurring) no concerns at is time
09/26/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
10/03/2023 SITE - Stormwater Follow-up Complete (Recurring) I drove through the project. There’s no concerns at this time for stormwater follow up.
10/10/2023 SITE - Stormwater Follow-up Complete (Recurring) All set up and controls are in place entire site very maintained and clean.
10/17/2023 SITE - Stormwater Follow-up Complete (Recurring) NO CONCERNS AT IS TIME
10/24/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
11/01/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time walked the site and everything still looks good
11/14/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time for this item
11/21/2023 SITE - Stormwater Follow-up Not Ready
11/28/2023 SITE - Stormwater Follow-up Complete (Recurring) Contractors continue to work on the roadways and sidewalks talk to the contractor this morning. He informed me that they will finish the channel area after they’re installed the sidewalks and paved roads.
12/05/2023 SITE - Stormwater Follow-up Complete (Recurring) spoke to the contractor borderland they informed me that the channel on the west side will be completed after they finish paving. The other channel between Home Depot and where borderland is it’s not gonna be completed until Home Depot paved the parking lot because they need to access through borderlands main road leading to Home Depot.
12/19/2023 SITE - Stormwater Follow-up Complete (Recurring) Contractors working on the channel at the west end of the project installing riprap filter fabric
12/26/2023 SITE - Stormwater Follow-up Partial Pass Contractors raising the utilities and adjustments