Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 04/13/2021 |
ENGR Grading Final |
MHERNADEZ |
Continued |
Entered by RSALDAT1 - NA |
| 11/15/2019 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by DMERANZ1 - Talked with water truck driver site foreman not on site today hauling dirt. |
| 01/10/2024 |
ENGR Grading Final |
|
Passed |
|
| 06/07/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractor informed me that they’re gonna start excavating for storm drain pipe on Monday will call in for an inspection on Monday |
| 06/12/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Mortal land install a 48 inch storm drain pipe on the north east part of the project. |
| 06/22/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractor is forming up a storm drain manhole on the north east side of the project. And installing 24 inch SRP’s on the east going west 160 lineal feet. |
| 06/27/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
contractor is forming for manhole for 32” storm drainage.will pour it later today |
| 06/27/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
contractor is forming for manhole for 32” storm drainage.will pour it later today |
| 11/15/2023 |
ENGR Grading Final |
|
Partial Pass |
Borderland continue to cut grade for sidewalk and ramps superintendent informed me that he would give me a call when the ramps are formed. |
| 11/21/2023 |
ENGR Grading Final |
|
Partial Pass |
|