Permit: DP17-0086
Permit Details
Status:
Complete
Type:
Development Package
Address:
2807 N CAMPBELL AV
Address NEW:
2807 N CAMPBELL AV
Apply Date:
04/13/2017
Applicant:
Brandy Burke
Description:
SITE/GRADING - STARBUCKS
Permit Reviews
Permit Number - DP17-0086
Permit Status: Complete
Permit Description: SITE/GRADING - STARBUCKS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/13/2017 | DEV PKG - OK TO SUBMIT | 04/13/2017 | COMPLETED |
| 04/13/2017 | DEV PKG | 05/16/2017 | COMPLETED |
| 07/14/2017 | DEV PKG - RESUBMITTAL | 08/14/2017 | COMPLETED |
| 08/21/2017 | DEV PKG - RESUBMITTAL | 08/24/2017 | ACTIVE |
Completed Inspections
Permit Status: Complete
Permit Number: DP17-0086
Permit Description: SITE/GRADING - STARBUCKS
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/08/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 12/08/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 12/08/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 12/08/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE IS LESS THAN 1 ACRE THEREFORE NO SWPPP IS REQUIRED 2) SWEEP UP TRACKED SOIL OFF ADJACENT ROADWAYS ROUTINELY 3) CALL FOR INSPECTIONFOR RE-BAR LAY OUT PRIOR TO COVERING. 4) CALL FOR INSPECTION FOR ANY SITE/GRADING/LANDSCAPING CONCERNS 5) CERT STATEMENT AND AS-BUILT REQUIRED PER APPROVED PLANS} |
|
| 05/03/2018 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 05/03/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/03/2018 | SITE - Stormwater Follow-up | Passed | {Activity date: 05/03/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 03/06/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PROGRESS INSPECTION, NO CONCERNS AT THIS TIME} ; {Activity date: 01/03/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME} | |
| 05/03/2018 | SITE - Stormwater Final Inspection | Passed | {Activity date: 05/03/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/15/2018 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 05/15/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/15/2018 | ENGR Grading Final | Passed | {Activity date: 05/15/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/15/2018 | COT - ENGR - Signage Final | Passed | {Activity date: 05/15/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 05/25/2018 | ENGR Engineering Final | Passed | {Activity date: 05/25/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 05/15/2018; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - AWAITING CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD AND COMPLETE LANDSCAPING - CALL FOR RE-INSPECTION} ; {Activity date: 05/03/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PREP FOR PAVING - SUB GRADE OK 2) RE-BAR FOR DRIVE THROUGH - OK 3) ENSURE PEDESTRIAN ACCESS FROM CAMPBEL MEETS ADA} |