Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/03/2018 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - LOOKED AT DRIVE THROUGH, RE-BAR INSTALLED PER APPROVED PLAN - OK FOR CONCRETE |
| 03/05/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - TRASH ENCLOSURE PAD AND APRON INSTALLED OK TO POUR CONCRETE |
| 01/03/2018 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - RE-BAR LAY OUT - BOND BEAM IN PLACE. VERTICALS IN PLACE , OK TO GROUT CELLS.
CALL FOR RE-INSPECTION FOR ENCLOSURE PAD |
| 12/28/2017 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - MET WITH THE DEVELOPER MW MORRISY AND DISCUSSED THE CURRENT WORK. THEY HAVE COMPLETED THE FIRST 4 FEET OF THE TRASH ENCLOSURE AND ARE READY TO PLACE THE GROUT INSIDE THE WALLS. ALL OTHER WALLS ON THE WEST SIDE OF THE SITE HAVE BEEN INSPECTED BY THE BUILDING INSPECTORS FOR THE GROUT INSTALLATION. |
| 12/20/2017 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - |
| 05/15/2018 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 05/15/2018 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 12/08/2017 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |