SITE/GRADING/SWPPP- SELF-STORAGE AT SUNSET RANCH

Permit Reviews

Permit Number - DP16-0206
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP- SELF-STORAGE AT SUNSET RANCH
Start Date Submittal Complete Date Status  
02/02/2017 DEV PKG - RESUBMITTAL 03/07/2017 COMPLETED Review Details
04/10/2017 DEV PKG - RESUBMITTAL 06/23/2017 COMPLETED Review Details
11/16/2016 DEV PKG - OK TO SUBMIT 11/18/2016 COMPLETED Review Details
11/18/2016 DEV PKG 01/23/2017 COMPLETED Review Details

Conditions

Permit Number - DP16-0206
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP- SELF-STORAGE AT SUNSET RANCH
Date Description Comments
05/10/2018 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
05/10/2018 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
05/10/2018 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: DP16-0206
Permite Description: SITE/GRADING/SWPPP- SELF-STORAGE AT SUNSET RANCH
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
05/30/2018 ENGR Engineering Final N/A Complete (Recurring) {Activity date: 05/30/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/30/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD, CALL FOR RE-INAPECTION} ; {Activity date: 04/30/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - COMPLETE CONSTRUCTION, CALL FOR RE-INSPECTION}

Completed Inspections

Permit Status: Complete
Permit Number: DP16-0206
Permit Description: SITE/GRADING/SWPPP- SELF-STORAGE AT SUNSET RANCH
Total Completed Inspections - 8
Date Description Inspector Results Comments
06/28/2017 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 06/28/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL SEDIMENT CONTROLS PER YOUR SWPPP
2) POST A COPY OF YOUR NOI AT ENTRANCE TO THE SITE
3) PERFORM STORM WATER SELF INSP PER YOUR SWPPP
4) INSTALL A CONCRETE WASH OUT
5) INSTALL A STABILIZED CONSTRUCTION ENTRANCE
6) CALL FOR INSPECTION FOR ANY SITE/GRADING/LANDSCAPING CONCERNS}
04/12/2018 PDSD Site/Engineering Division - NPPO Passed {Activity date: 04/12/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/12/2018 SITE - Stormwater Setup and Controls Passed {Activity date: 04/12/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }
04/30/2018 SITE - Stormwater Final Inspection Passed {Activity date: 04/30/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - FILE A NOTICE OF TERMINATION WITH ADEQ}
05/07/2018 SITE - Stormwater Follow-up Passed {Activity date: 05/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/18/2018; Status: Continued; Inspector: DROBERT5; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/26/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE IS UNDER AN AZPDES PERMIT AND SWPPP UNTIL THE SITE IS STABILIZED PER THE APPROVED PLANS.
2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION.
3) CONTINUE TO SWEEP UP TRACKED SOIL ROUTINELY} ; {Activity date: 09/29/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LOOKED AT LAST CATCH BASIN INSTALL AND PIPE TRANSITION. OK TO COVER
2) SWEEP UP TRACKED SOIL OFF SILVERBELL
3) RE-ESTABLISH YOU STABILIZED CONSTRUCTION ENTRANCE} ; {Activity date: 09/14/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) LOOKED AT CATCH BASIN INSTALL ALONG E SIDE OF SITE AT SRP TIE-IN, GROUT OK, OK TO COVER - PICS TAKEN
2) ENSURE YOUR STABILIZED CONSTRUCTION ENTRANCE IS MAINTAINED THROUGHOUT CONSTRUCTION
3) MAINTAIN PERIMETER SEDIMENT CONTROLS AS NEEDED
4) PERFORM STORM WATER SELF INSPECTIONS AND DOCUMENT THEM} ; {Activity date: 08/23/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROGRESS CHECK OF INSTALL OF 24"SRP AND PRE-CAST CATCH BASINS
2) TOOK PICTURES OF SET CATCH BASINS AND GROUTING OF PIPE - OK
3) TOOK PICTURES OF DRAINAGE CHANNEL PROGRESS ALONG THE EAST SIDE
4) SWEEP UP TRACKED SOIL
5) ENSURE SAFETY RAILING ALONG RET/DET BASIN AND DRAINAGE CHANNEL IS ADDRESSED} ; {Activity date: 08/14/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SWEEP UP TRACKING OFF OF PUBLIC ROADWAY.
2) RE-ESTABLISH STABILIZED CONSTRUCTION ENTRANCE.
3) SITE IS SATURATED AND CONCRETE WORK HAS BEEN POSTPONED} ; {Activity date: 08/09/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SEDIMENT CONTROLS ARE IN PLACE ALONG THE NORTH SIDE OF THE SITE; HOWEVER STORM WATER REG WILL CHANGE AS CONSTRUCTION ADVANCES
2) LOOKED AT A SECTION OF STORM CHANNEL ALONG EAST SIDE OF SITE - SHOTCRETE THIS WEEK
3) CALL FOR RE-INSPECTIOBN PRIOR TO COVERING STORM PIPE AND CATCH BASINS} ; {Activity date: 08/03/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) INSTALL OF 24' RCP ALONG NORTH SIDE OF SITE
2) ENSURE COMPACTION AND BEDDING OF PIPE PER MANUFACTURER SPECS
3) CALL FOR RE-INSP PRIOR TO COVER OF PIPE

PICS TAKEN
4) ENSURE SWPP IS INSTALLED PER YOUR PLAN}
05/30/2018 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 05/30/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 05/07/2018; Status: Denied; Inspector: MRUSSO; Comment: Entered by DROBERT5 - DENIED, COMPLETE ALL LANDSCAPING PER THE APPROVED PLANS}
05/30/2018 ENGR Grading Final Passed {Activity date: 05/30/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 04/03/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) PROGRESS INSPECTION, CONTRCTOR WORKING ON PREP FOR PAVING. INSTALL OF CURBING AND VALLEY GUTTER PER PLAN.
2) CALL FOR INSPECTION FOR RE-BAR LAY OUT FOR TRASH ENCLOSURE PAD}
05/30/2018 COT - ENGR - Signage Final Passed {Activity date: 05/30/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
001_COVER SHEET / NOTES_1 OF 24.TIF DEVELOPMENT PACKAGE VIEW
002_REZONING CONDITIONS / GRADING / PAVING NOTES_2 OF 24.TIF DEVELOPMENT PACKAGE VIEW
003_PRIVATE UTILITY NOTES_3 OF 24.TIF DEVELOPMENT PACKAGE VIEW
004_SITE_4 OF 24.TIF DEVELOPMENT PACKAGE VIEW
005_SITE_5 OF 24.TIF DEVELOPMENT PACKAGE VIEW
006_GRADING / PAVING_6 OF 24.TIF DEVELOPMENT PACKAGE VIEW
007_GRADING / PAVING_7 OF 24.TIF DEVELOPMENT PACKAGE VIEW
008_GRADING / PAVING_8 OF 24.TIF DEVELOPMENT PACKAGE VIEW
009_SITE / GRADING / UTILITY DETAILS_9 OF 24.TIF DEVELOPMENT PACKAGE VIEW
010_SITE / GRADING DETAILS_10 OF 24.TIF DEVELOPMENT PACKAGE VIEW
011_HORIZONTAL CONTROL / DATA_11 OF 24.TIF DEVELOPMENT PACKAGE VIEW
012_PRIVATE UTILITY_12 OF 24.TIF DEVELOPMENT PACKAGE VIEW
013_PRIVATE UTILITY_13 OF 24.TIF DEVELOPMENT PACKAGE VIEW
014_SWPPP_14 OF 24.TIF DEVELOPMENT PACKAGE VIEW
015_LANDSCAPE NOTES_15 OF 24.TIF DEVELOPMENT PACKAGE VIEW
016_LANDSCAPE DETAILS_16 OF 24.TIF DEVELOPMENT PACKAGE VIEW
017_LANDSCAPE SPECIFICATIONS_17 OF 24.TIF DEVELOPMENT PACKAGE VIEW
018_LANDSCAPE SPECIFICATIONS_18 OF 24.TIF DEVELOPMENT PACKAGE VIEW
019_PLANTING / IRRIGATION LEGENDS_19 OF 24.TIF DEVELOPMENT PACKAGE VIEW
020_PLANTING_20 OF 24.TIF DEVELOPMENT PACKAGE VIEW
021_PLANTING_21 OF 24.TIF DEVELOPMENT PACKAGE VIEW
022_IRRIGATION_22 OF 24.TIF DEVELOPMENT PACKAGE VIEW
023_IRRIGATION_23 OF 24.TIF DEVELOPMENT PACKAGE VIEW
024_WATER HARVESTING IMPLEMENTATION_24 OF 24.TIF DEVELOPMENT PACKAGE VIEW
RWRD ACCEPTANCE.PDF DOCUMENTS VIEW
BUILDING ELEVATIONS.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT.PDF DOCUMENTS VIEW
NPPO EXCEPTION APPLICATION.PDF DOCUMENTS VIEW
SWPPP.PDF DOCUMENTS VIEW
DP RESP LTR 1ST.PDF DOCUMENTS VIEW
BUILDING COLOR PALETTES.PDF DOCUMENTS VIEW
BUILDING FLOOR PLANS.PDF DOCUMENTS VIEW
EMAIL FROM TDOT ALLOWING 10 SCZ IN ROW.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT ADDENDUM 1.PDF DOCUMENTS VIEW
LETTER OF COMPLIANCE TO REZONING CONDITIONS.PDF DOCUMENTS VIEW
DP RESP LTR 2ND.PDF DOCUMENTS VIEW
EMAIL APPROVAL FROM TDOT LANDSCAPE ARCHITECT.PDF DOCUMENTS VIEW
EMAIL FROM TDOT ALLOWING OFFSET CONSTRUCTION CENTERLINE.PDF DOCUMENTS VIEW
UPDATED DRAINAGE REPORT.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW